Completion Date
November 2023
Status Updated
May, 2022
Name Of The Work | Progress Details (Current Month) | Remarks |
Foundation Work. | 100% Completed | |
Super Structure Work | 100% Completed | |
Block Work | 95% Completed | |
Electrical Conduiting Work | 90% Completed | |
Door Frame Fitting Work | 90% Completed | |
Sanitary & Plumbing Line Work | 80% Completed | |
In Side Plastering Work | 70% Completed | |
Electrical Cable Wiring Work | 50% Completed | |
Wall tiles Work | 80% Completed | |
Common Sanitary & Plumbing Line Work | 30% Completed | |
Outside Plastering Work | Nill | |
Floor Tiles/Marble Work | 40% Completed | |
L.C.C Work | Nill | |
Grill & Railing Work | N/A | |
Inside Paint & Polishing Work | N/A | |
Switch-Socket Fitting Work | N/A | |
Outside Paint Work | N/A | |
Door Shutter Work | N/A | |
Aluminum/Glazing Work | N/A | |
Tiles Pointing Work & Marble Finishing Work | N/A | |
Commode - Basin Fitting Work and C.P Fittings Work | N/A | |
Lift/Generator /Substation /Solar Work | N/A | |
Boundary Wall /Ground Floor Development Work | N/A | |
Roof Top Finishing Work | N/A | |
Roof Top Gardening Work | N/A |