Completion Date
November 2023
Status Updated
May, 2023
SL. No | Name of the work | Progress details |
01 | Foundation work | 100% Completed |
02 | Super Structure work | 100% Completed |
03 | Block work | 100% Completed |
04 | Electrical conduiting work | 100% Completed |
05 | Door frame fitting work | 100% Completed |
06 | Sanitary & plumbing line work | 100% Completed |
07 | In side Plastering work | 100% Completed |
08 | Electrical cable wiring work | 100% Completed |
09 | Wall tiles work | 100% Completed |
10 | Common sanitary & Plumbing line work | 98% Completed |
11 | Outside plastering work | 100% Completed |
12 | Floor tiles/Marble work | 100% Completed |
13 | L.C.C work | 100% Completed |
14 | Grill & Railing work | 100% Completed |
15 | Inside paint & Polishing work | 70% |
16 | Switch -Socket fitting work | 95% |
17 | Outside paint work | 60% |
18 | Door shutter work | 95% |
19 | Aluminum/Glazing work | 80% |
20 | Tiles Pointing work (Wall) & Marble finishing work | Wall 100% floor 40% |
21 | Commode – Basin fitting work and C.P fittings work | 80% |
22 | Lift/Generator /Substation /Solar work | 50% |
23 | Boundary wall /Ground floor development work | 100% Completed |
24 | Roof top finishing work | 90% Completed |
25 | Roof top Gardening work | 60% Completed |