Dolce Vita

Joar Shahara, Dhaka

Completion Date

November 2023

Status Updated

May, 2023

SL. No Name of the work Progress details
01 Foundation work 100% Completed
02 Super Structure work 100% Completed
03 Block work 100% Completed
04 Electrical conduiting work 100% Completed
05 Door frame fitting work 100% Completed
06 Sanitary & plumbing line work 100% Completed
07 In side Plastering work 100% Completed
08 Electrical cable wiring work 100% Completed
09 Wall tiles work 100% Completed
10 Common sanitary & Plumbing line work 98% Completed
11 Outside plastering work 100% Completed
12 Floor tiles/Marble work 100% Completed
13 L.C.C work 100% Completed
14 Grill & Railing work 100% Completed
15 Inside paint & Polishing work 70%
16 Switch -Socket fitting work 95%
17 Outside paint work 60%
18 Door shutter work 95%
19 Aluminum/Glazing work 80%
20 Tiles Pointing work (Wall) & Marble finishing work Wall 100% floor 40%
21 Commode – Basin fitting work and C.P fittings work 80%
22 Lift/Generator /Substation /Solar work 50%
23 Boundary wall /Ground floor development work 100% Completed
24 Roof top finishing work 90% Completed
25 Roof top Gardening work 60% Completed