Glenwood

Wari, Dhaka

Completion Date

February 2024

Status Updated

March, 2024

SL. No Name of the work Progress details

(March’24)

01 Foundation work 100% completed.
02 Super Structure work 100% completed.
03  

 

Block Work

GF=100%& Roof top=100%

A1=100%,B1=100%

A2=100%,B2=100%

A3=100%,B3=100%

A4=100%, B4=100%

A5=100%.B5=100%

A6=100% , B6=100%

A7=100% ,B7=100%

A8=100% ,B8=100%

A9=100% & B9=100%

04 Electrical Conducting work GF=100%& Roof top=100%

A1=100%,B1=100%

A2=100%,B2=100%

A3=100%,B3=100%

A4=100%, B4=100%

A5=100%.B5=100%

A6=100% , B6=100%

A7=100% ,B7=100%

A8=100% ,B8=100%

A9=100% & B9=100%

 

05 Door frame fitting work GF=100% & Roof top=100%

A1=100%,B1=100%

A2=100%,B2=100%

A3=100%,B3=100%

A4=100%, B4=100%

A5=100%.B5=100%

A6=100% , B6=100%

A7=100% ,B7=100%

A8=100% ,B8=100%

A9=100% & B9=100%

06  

 

Sanitary & plumbing line  work

GF=100% & Roof top=100%

A1=100%,B1=100%

A2=100% ,B2=100%

A3=100%,B3=100%

A4=100%, B4=100%

A5=100%.B5=100%

A6=100% , B6=100%

A7=100% ,B7=100%

A8=100% ,B8=100%

A9=100% & B9=100%

 

07  

 

In side Plastering work

GF=100% Roof top=100%

A1=100%,B1=100%

A2=100%,B2=100%

A3=100%,B3=100%

A4=100%, B4=100%

A5=100%.B5=100%

A6=100% , B6=100%

A7=100% ,B7=100%

A8=100% ,B8=100%

A9=100% & B9=100%

08  

 

Electrical cable wiring work

GF=100% Roof top=100%

A1=100%,B1=100%

A2=100%,B2=100%

A3=100%,B3=100%

A4=100%, B4=100%

A5=100%.B5=100%

A6=100% , B6=100%

A7=100% ,B7=100%

A8=100% ,B8=100%

A9=100% & B9=100%

 

09  

 

Wall tiles work

GF=100%         Roof top= 100%

A1=100%,B1=100%

A2=100%,B2=100%

A3=100%,B3=100%

A4=100%, B4=100%

A5=100%.B5=100%

A6=100% , B6=100%

A7=100% ,B7=100%

A8=100% ,B8=100%

A9=100% & B9=100%

10  

 

Common sanitary & Plumbing line work

GF=100% Roof top=100%

A1=100%,B1=100%

A2=100%,B2=100%

A3=100%,B3=100%

A4=100%, B4=100%

A5=100%.B5=100%

A6=100% , B6=100%

A7=100% ,B7=100%

A8=100% ,B8=100%

A9=100% & B9=100%

 

11 Outside plastering work  

patch work ongoing

12  

 

Floor tiles/Marble work

 

 

Flat area 100 % Completed

13 L.C.C work 100% completed
14 Grill & Railing work GF=100% Roof top =100%

A1=100%,B1=100%

A2=100%,B2=100%

A3=100%,B3=100%

A4=100%, B4=100%

A5=100%.B5=100%

A6=100% , B6=100%

A7=100% ,B7=100%

A8=100% ,B8=100%

A9=100% & B9=100%

15 Inside paint & Polishing work 100 % Completed 3rd coat
16 Switch -Socket fitting work GF=100% Roof top =100%

A1=100%,B1=100%

A2=100%, B2=100%

A3=100% , B3=100%

A4=100%, B4100%

A5=100%.B5=100%

A6=100% , B6=100%

A7=100% ,B7=100%

A8=100% ,B8=100%

A9=100% & B9=100%

17 Outside paint work 90 % Completed

2nd coat

18 Door shutter work GF=100% Roof top =100%

A1=100%,B1=100%

A2=100%, B2=100%

A3=100%, B3=100%

A4=100%, B4=100%

A5=100% B5=100%

A6=100% ,  B6=100%

A7=100% ,B7=100 %

A8=100% ,B8=100%

A9=100% & B9=100

19 Aluminum work GF=100% Roof top =100%

A1=100%,B1=100%

A2=100%,B2=100 %

A3=100%,B3=100%

A4=100%, B4=100%

A5=100%.B5=100%

A6=100% , B6=100%

A7=100% ,B7=100%

A8=100% ,B8=100%

A9=100% & B9=100%

20 Tiles Pointing work & Marble finishing work GF=99% Roof top =100%

A1=100%,B1=100%

A2=100%,B2=100 %

A3=100%,B3=40 %

A4=100%, B4=100%

A5=100%.B5=100%

A6=100% , B6=100%

A7=100% ,B7=100%

A8=100% ,B8=100%

A9=100% & B9=100%

21 Commode – Basin fitting work and C.P fittings work GF=100% Roof top NA

A1=100%,B1=100%

A2=100%,B2=100 %

A3=100%,B3=100%

A4=100%, B4=100%

A5=100%.B5=100%

A6=100% , B6=100%

A7=100% ,B7=100 %

A8=100% ,B8=100 %

A9=100% & B9=100%

22 Lift/Generator /Substation /Solar work Generator Testing ok

 

23 Boundary wall /Ground floor development work Ground floor M.S work some done
24 Roof top finishing work Water body work  100% completed
25 Roof top Gardening work G.F Garden work Roof top gardening civil work completed.