Completion Date
February 2024
Status Updated
March, 2024
SL. No | Name of the work | Progress details
(March’24) |
01 | Foundation work | 100% completed. |
02 | Super Structure work | 100% completed. |
03 |
Block Work |
GF=100%& Roof top=100%
A1=100%,B1=100% A2=100%,B2=100% A3=100%,B3=100% A4=100%, B4=100% A5=100%.B5=100% A6=100% , B6=100% A7=100% ,B7=100% A8=100% ,B8=100% A9=100% & B9=100% |
04 | Electrical Conducting work | GF=100%& Roof top=100%
A1=100%,B1=100% A2=100%,B2=100% A3=100%,B3=100% A4=100%, B4=100% A5=100%.B5=100% A6=100% , B6=100% A7=100% ,B7=100% A8=100% ,B8=100% A9=100% & B9=100%
|
05 | Door frame fitting work | GF=100% & Roof top=100%
A1=100%,B1=100% A2=100%,B2=100% A3=100%,B3=100% A4=100%, B4=100% A5=100%.B5=100% A6=100% , B6=100% A7=100% ,B7=100% A8=100% ,B8=100% A9=100% & B9=100% |
06 |
Sanitary & plumbing line work |
GF=100% & Roof top=100%
A1=100%,B1=100% A2=100% ,B2=100% A3=100%,B3=100% A4=100%, B4=100% A5=100%.B5=100% A6=100% , B6=100% A7=100% ,B7=100% A8=100% ,B8=100% A9=100% & B9=100%
|
07 |
In side Plastering work |
GF=100% Roof top=100%
A1=100%,B1=100% A2=100%,B2=100% A3=100%,B3=100% A4=100%, B4=100% A5=100%.B5=100% A6=100% , B6=100% A7=100% ,B7=100% A8=100% ,B8=100% A9=100% & B9=100% |
08 |
Electrical cable wiring work |
GF=100% Roof top=100%
A1=100%,B1=100% A2=100%,B2=100% A3=100%,B3=100% A4=100%, B4=100% A5=100%.B5=100% A6=100% , B6=100% A7=100% ,B7=100% A8=100% ,B8=100% A9=100% & B9=100%
|
09 |
Wall tiles work |
GF=100% Roof top= 100%
A1=100%,B1=100% A2=100%,B2=100% A3=100%,B3=100% A4=100%, B4=100% A5=100%.B5=100% A6=100% , B6=100% A7=100% ,B7=100% A8=100% ,B8=100% A9=100% & B9=100% |
10 |
Common sanitary & Plumbing line work |
GF=100% Roof top=100%
A1=100%,B1=100% A2=100%,B2=100% A3=100%,B3=100% A4=100%, B4=100% A5=100%.B5=100% A6=100% , B6=100% A7=100% ,B7=100% A8=100% ,B8=100% A9=100% & B9=100%
|
11 | Outside plastering work |
patch work ongoing |
12 |
Floor tiles/Marble work |
Flat area 100 % Completed |
13 | L.C.C work | 100% completed |
14 | Grill & Railing work | GF=100% Roof top =100%
A1=100%,B1=100% A2=100%,B2=100% A3=100%,B3=100% A4=100%, B4=100% A5=100%.B5=100% A6=100% , B6=100% A7=100% ,B7=100% A8=100% ,B8=100% A9=100% & B9=100% |
15 | Inside paint & Polishing work | 100 % Completed 3rd coat |
16 | Switch -Socket fitting work | GF=100% Roof top =100%
A1=100%,B1=100% A2=100%, B2=100% A3=100% , B3=100% A4=100%, B4100% A5=100%.B5=100% A6=100% , B6=100% A7=100% ,B7=100% A8=100% ,B8=100% A9=100% & B9=100% |
17 | Outside paint work | 90 % Completed
2nd coat |
18 | Door shutter work | GF=100% Roof top =100%
A1=100%,B1=100% A2=100%, B2=100% A3=100%, B3=100% A4=100%, B4=100% A5=100% B5=100% A6=100% , B6=100% A7=100% ,B7=100 % A8=100% ,B8=100% A9=100% & B9=100 |
19 | Aluminum work | GF=100% Roof top =100%
A1=100%,B1=100% A2=100%,B2=100 % A3=100%,B3=100% A4=100%, B4=100% A5=100%.B5=100% A6=100% , B6=100% A7=100% ,B7=100% A8=100% ,B8=100% A9=100% & B9=100% |
20 | Tiles Pointing work & Marble finishing work | GF=99% Roof top =100%
A1=100%,B1=100% A2=100%,B2=100 % A3=100%,B3=40 % A4=100%, B4=100% A5=100%.B5=100% A6=100% , B6=100% A7=100% ,B7=100% A8=100% ,B8=100% A9=100% & B9=100% |
21 | Commode – Basin fitting work and C.P fittings work | GF=100% Roof top NA
A1=100%,B1=100% A2=100%,B2=100 % A3=100%,B3=100% A4=100%, B4=100% A5=100%.B5=100% A6=100% , B6=100% A7=100% ,B7=100 % A8=100% ,B8=100 % A9=100% & B9=100% |
22 | Lift/Generator /Substation /Solar work | Generator Testing ok
|
23 | Boundary wall /Ground floor development work | Ground floor M.S work some done |
24 | Roof top finishing work | Water body work 100% completed |
25 | Roof top Gardening work G.F Garden work | Roof top gardening civil work completed. |