Ikebana

Uttara, Dhaka

Completion Date

To be Announced

Status Updated

March, 2024

SL. No Name of the work Progress details
1 Foundation work 100% complete.
2 Basement work N/A
3 Super Structure work 100% complete.
4 Block Work 100% completed
5 Electrical conduiting work 100% completed
6 Door frame fitting work 100% completed
7 Sanitary & plumbing line work 100% completed
8 Inside Plastering work 100% completed
9 Electrical cable wiring work 100% completed
10 Wall tiles work 100% completed
11 Common sanitary & Plumbing line work 100% completed
12 Outside plastering work 100% completed
13 Floor tiles/Marble work 100% completed
14 L.C.C work 100% completed
15 Grill & Railing work 100% completed
16 Inside paint & Polishing work 98% completed
17 Switch -Socket fitting work 99% completed
18 Outside paint work 90% completed
19 Door shutter work 100% completed
20 Aluminum work 100% completed
21 Tiles Pointing work & Marble finishing work 98% completed
22 Commode – Basin fitting work and C.P fittings work 100% completed
23 Lift/Generator /Substation /Solar work Lift Work 90%, Generator received, Substation work 100%, Solar work 100% completed
24 Boundary wall /Ground floor development work 98% completed
25 Roof top finishing work 98% completed
26 Roof top Gardening work G.F Garden work 80% completed
27 Land escape /Logo work 80% completed