Completion Date
February 2024
Status Updated
August, 2024
SL. No | Name of the work | Progress details |
01 | Foundation work | 100% completed. |
02 | Super Structure work | 100% completed. |
03 | Block Work | 100 % completed. |
04 | Electrical conducting work | 100 % completed. |
05 | Door frame fitting work | 100% completed. |
06 | Sanitary & plumbing line work | 95 % completed. |
07 | In side Plastering work | 100 % completed. |
08 | Electrical cable wiring work | 95 % completed. |
09 | Wall tiles work | 95 % completed. |
10 | Common sanitary & Plumbing line work | 90 % completed. |
11 | Outside plastering work | 100% completed. |
12 | Floor tiles/Marble work | 95 % completed |
13 | L.C.C work | 100% completed |
14 | Grill & Railing work | 95% completed |
15 | Inside paint & Polishing work | 60 % completed |
16 | Switch -Socket fitting work | 0% completed |
17 | Outside paint work | 10% completed |
18 | Door shutter work | 0% completed, main door |
19 | Aluminum work | 60% completed |
20 | Tiles Pointing work & Marble finishing work | 0% completed |
21 | Commode – Basin fitting work and C.P fittings work | 0% completed |
22 | Lift/Generator /Substation /Solar work | 0% completed |
23 | Boundary wall /Ground floor development work | 60% completed. |
24 | Roof top finishing work | 80% completed. |
25 | Roof top Gardening work G.F Garden work | 0% completed. |
16604