Completion Date
December 2022
Status Updated
July, 2022
SL | Progress details | |
01 | Foundation work | 100% completed. |
02 | Super Structure work | T-1. 6th floor roof slab casting- 100% completed.
T-2. 6th floor roof slab- 100% completed. T-3. 6th floor roof slab casting -100% completed. T-4. 6th floor roof slab casting -100% complete. T-5. 6th.floor roof slab casting100% completed. T-6. 6th floor roof slab casting 100% completed. T-7. 6th floor roof slab casting -100% completed. Mini Amphitheatre work -100% complete. |
03 | Block Work | Tower-1) A1,B1,C1,D1- 100% , A2,B2,C2,D2- 100% ,A3,B3,C3D3-100%,A4,B4,C4,D4-100%.A5,B5,C5,D5-100%,A6,B6,C6,D6 100%completed.
Towe-2) A1,B1,C1,D1 100% & A2,B2,C2,D2 – 100% & A3,B3,C3,D3 – 100%.A4,B4,C4,D4, -100%.A5,B5,C5,D5-100% A6,B6,C6,D6-100% completed. T-3) A1,B1,C1,D1,E1,F1, -100% & A2,B2,C2,D2,E2,F2- 100% A3,B3,C3,D3,E3,F3 -100% & A4,B4,C4,D4,E4,F4-100%.A5,B5,C5,D5,E5,F5-100%. A6,B6,C6,D6,E6,F6 100% completed. T-4) A1,B1,C1,D1,- 100% & A2,B2,C2,D2 – 100% & A3,B3,C3,D3 -100%.A4,B4,C4,D4- 100%. A5,B5,C5,D5- 100% .A6,B6,C6,D6 100% completed. T-5) A1,B1,C1,D1,E1,F1,G1,H1 – 100%.A2,B2,C2,D2,E2,F2,G2,H2 -100% .A3,B3,C3,D3, E3,F3,G3,H3 – 100%.A4,B4,C4,D4,E4,F4,G4,H4-100% .A5,B5,C5,D5-100%,E5,F5,G5,H5 -100%.A6,B6,C6,D6, E6,F6,G6,H6-100% completed. T-6) A1,B1,C1,D1,E1,F1,G1,H1 -100% & A2,B2,C2,D2,E2.F2,G2,H2 – 100% A3,B3,C3,D3,E3,F3,G3,H3 -100% .A4,B4,C4,D4,E4,F4,G4,H4 100%. A5,B5,C5,D5,E5,F5,G5,H5-100%. A6,B6,C6,D6,E6,F6,G6,H6- 100% completed. T-7) A1,B1,C1,D1, -100% & A2,B2,C2,D2,E2,F2- 100% A3,B3,C3,D3- 100%, A4,B4,C4,D4 ,-100%,A5,B5,C5,D5-100% A6,B6,C6,D6-100% completed. |
04 | Electrical conduit work | 1) 1st floor -100% , 2nd floor -100%,3RD.FLloor-100%4rth floor.100%.5th.ffloor 100%,6th.floor 100% completed. |
05 | Door frame fitting work | 100% |
06 | Sanitary & plumbing line work | 100% |
07 | In side Plastering work | 1) Basement. floor ceiling plaster100% completed.
2) Ground. floor ceiling plaster -100% completed. 3) 1st floor ceiling plaster – 100% completed. 4) 2nd floor ceiling plaster-100% completed. 5) 3rd floor ceiling plaster -100% completed. 6)4rth floor ceiling plaster -100% completed. 7) 5th floor ceiling plaster-100% completed 8)6th floor ceiling plaster -100% completed. 9) Internal wall plaster all tower-100% completed.
|
08 | Electrical cable wiring work | 98%(all tower) Completed |
09 | Wall tiles work | 100%(all tower) Completed |
10 | Common sanitary & Plumbing line work | 85% |
11 | Outside plastering work | 98%(all tower) Completed |
12 | Floor tiles/Marble work | 97% Completed |
13 | L.C.C work | 100% |
14 | Grill & Railing work | 96% Completed |
15 | Inside paint & Polishing work | 65% |
16 | Switch -Socket fitting work | On going |
17 | Outside paint work | 65% |
18 | Door shutter work | On going |
19 | Aluminum/Glazing work | 75% |
20 | Tiles Pointing work & Marble finishing work | On going |
21 | Commode – Basin fitting work and C.P fittings work | On going |
22 | Lift/Generator /Substation /Solar work | 25% |
23 | Boundary wall /Ground floor development work | 72% completed |
24 | Roof top finishing work | 65% |
25 | Roof top Gardening work | 55% |