Shopnobilash

Savar, Dhaka

Completion Date

December 2022

Status Updated

July, 2022

SL   Progress details
01 Foundation work 100% completed.
02 Super Structure work T-1. 6th floor roof slab casting- 100% completed.

T-2. 6th  floor roof slab- 100% completed.

T-3. 6th floor roof slab casting  -100% completed.

T-4. 6th floor roof slab casting -100% complete.

T-5. 6th.floor roof slab casting100%  completed.

T-6. 6th floor roof slab casting  100% completed.

T-7. 6th floor roof slab casting -100% completed.

Mini Amphitheatre work -100% complete.

03 Block Work Tower-1) A1,B1,C1,D1- 100% , A2,B2,C2,D2- 100% ,A3,B3,C3D3-100%,A4,B4,C4,D4-100%.A5,B5,C5,D5-100%,A6,B6,C6,D6 100%completed.

Towe-2) A1,B1,C1,D1  100% & A2,B2,C2,D2 – 100%  & A3,B3,C3,D3 – 100%.A4,B4,C4,D4, -100%.A5,B5,C5,D5-100% A6,B6,C6,D6-100% completed.

T-3) A1,B1,C1,D1,E1,F1, -100%  &  A2,B2,C2,D2,E2,F2- 100%  A3,B3,C3,D3,E3,F3  -100% & A4,B4,C4,D4,E4,F4-100%.A5,B5,C5,D5,E5,F5-100%.  A6,B6,C6,D6,E6,F6 100% completed.

T-4) A1,B1,C1,D1,-  100% &  A2,B2,C2,D2 – 100%  & A3,B3,C3,D3 -100%.A4,B4,C4,D4-  100%. A5,B5,C5,D5-  100% .A6,B6,C6,D6 100%

completed.

T-5) A1,B1,C1,D1,E1,F1,G1,H1 – 100%.A2,B2,C2,D2,E2,F2,G2,H2 -100% .A3,B3,C3,D3, E3,F3,G3,H3 – 100%.A4,B4,C4,D4,E4,F4,G4,H4-100% .A5,B5,C5,D5-100%,E5,F5,G5,H5 -100%.A6,B6,C6,D6, E6,F6,G6,H6-100%  completed.

T-6) A1,B1,C1,D1,E1,F1,G1,H1 -100%  &  A2,B2,C2,D2,E2.F2,G2,H2 – 100%   A3,B3,C3,D3,E3,F3,G3,H3 -100% .A4,B4,C4,D4,E4,F4,G4,H4  100%. A5,B5,C5,D5,E5,F5,G5,H5-100%. A6,B6,C6,D6,E6,F6,G6,H6- 100% completed.

T-7) A1,B1,C1,D1, -100%  &  A2,B2,C2,D2,E2,F2-  100% A3,B3,C3,D3- 100%, A4,B4,C4,D4 ,-100%,A5,B5,C5,D5-100% A6,B6,C6,D6-100%  completed.

04 Electrical  conduit work 1) 1st floor -100% , 2nd floor -100%,3RD.FLloor-100%4rth floor.100%.5th.ffloor 100%,6th.floor 100% completed.
05 Door frame fitting work 100%
06 Sanitary & plumbing line  work 100%
07 In side Plastering work 1) Basement. floor ceiling plaster100% completed.

2) Ground. floor ceiling plaster -100% completed.

3) 1st floor ceiling plaster – 100% completed.

4) 2nd floor ceiling plaster-100% completed.

5) 3rd floor ceiling plaster -100% completed.

6)4rth floor ceiling plaster -100% completed.

7) 5th floor ceiling plaster-100% completed

8)6th floor ceiling plaster -100% completed.

9) Internal wall plaster all tower-100% completed.

 

08 Electrical cable wiring work 98%(all tower) Completed
09 Wall tiles  work 100%(all tower) Completed
10 Common sanitary & Plumbing line work 85%
11 Outside plastering work 98%(all tower) Completed
12 Floor tiles/Marble work 97% Completed
13 L.C.C work 100%
14 Grill & Railing work 96% Completed
15 Inside paint & Polishing work 65%
16 Switch -Socket fitting work On going
17 Outside paint work 65%
18 Door shutter work On going
19 Aluminum/Glazing work 75%
20 Tiles Pointing work & Marble finishing work On going
21 Commode – Basin fitting work and C.P fittings work On going
22 Lift/Generator /Substation /Solar work 25%
23 Boundary wall /Ground floor development work 72% completed
24 Roof top finishing work 65%
25 Roof top Gardening work 55%