Silver Wood

Aftabnagar, Dhaka

Completion Date

June 2024

Status Updated

March, 2024

SL. No Name of the work Location Progress details
01 Foundation work   100% Completed.
02 Super Structure work   99% Completed
03 Block Work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =B1

Apartment =B2

Apartment =B3

Apartment =B4

Apartment =B5

Apartment =B6

Apartment =B7

Apartment =C1

Apartment =C2

Apartment =C3

Apartment =C4

Apartment =C5

Apartment =C6

Apartment =C7

Apartment =C8

 

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

99% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

04 Electrical conduiting work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =B1

Apartment =B2

Apartment =B3

Apartment =B4

Apartment =B5

Apartment =B6

Apartment =B7

Apartment =C1

Apartment =C2

Apartment =C3

Apartment =C4

Apartment =C5

Apartment =C6

Apartment =C7

Apartment =C8

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

98% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

98% Completed

05 Door frame fitting work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =B1

Apartment =B2

Apartment =B3

Apartment =B4

Apartment =A5

Apartment =B6

Apartment =B7

Apartment =C1

Apartment =C2

Apartment =C3

Apartment =C4

Apartment =C5

Apartment =C6

Apartment =C7

Apartment =C8

 

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

100% Completed

06 Sanitary & plumbing line work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =B1

Apartment =B2

Apartment =B3

Apartment =B4

Apartment =A5

Apartment =B6

Apartment =B7

Apartment =C1

Apartment =C2

Apartment =C3

Apartment =C4

Apartment =C5

Apartment =C6

Apartment =C7

Apartment =C8

 

95% Completed

70% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

70% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

07 In side Plastering work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =B1

Apartment =B2

Apartment =B3

Apartment =B4

Apartment =A5

Apartment =B6

Apartment =B7

Apartment =C1

Apartment =C2

Apartment =C3

Apartment =C4

Apartment =C5

Apartment =C6

Apartment =C7

Apartment =C8

 

99% Completed

50% Completed

99% Completed

99% Completed

99% Completed

99% Completed

99% Completed

99% Completed

50% Completed

99% Completed

99% Completed

99% Completed

99% Completed

99% Completed

99% Completed

99% Completed

99% Completed

99% Completed

99% Completed

99% Completed

98% Completed

98% Completed

08 Electrical cable wiring work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =B1

Apartment =B2

Apartment =B3

Apartment =B4

Apartment =A5

Apartment =B6

Apartment =B7

Apartment =C1

Apartment =C2

Apartment =C3

Apartment =C4

Apartment =C5

Apartment =C6

Apartment =C7

Apartment =C8

 

90% Completed

20% Completed

90% Completed

90% Completed

90% Completed

90% Completed

90% Completed

90% Completed

20% Completed

90% Completed

90% Completed

90% Completed

90% Completed

90% Completed

90% Completed

90% Completed

90% Completed

90% Completed

90% Completed

90% Completed

90% Completed

90% Completed

09 Wall tiles work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =B1

Apartment =B2

Apartment =B3

Apartment =B4

Apartment =A5

Apartment =B6

Apartment =B7

Apartment =C1

Apartment =C2

Apartment =C3

Apartment =C4

Apartment =C5

Apartment =C6

Apartment =C7

Apartment =C8

 

95% Completed

20% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

50% Completed

20% Completed

90% Completed

90% Completed

90% Completed

90% Completed

90% Completed

90% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

10 Common sanitary & Plumbing line work   70% Completed

 

11 Outside plastering work   85% Completed
12 Floor tiles/Marble work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =B1

Apartment =B2

Apartment =B3

Apartment =B4

Apartment =A5

Apartment =B6

Apartment =B7

Apartment =C1

Apartment =C2

Apartment =C3

Apartment =C4

Apartment =C5

Apartment =C6

Apartment =C7

Apartment =C8

 

90% Completed

0% Completed

90% Completed

90% Completed

90% Completed

90% Completed

90% Completed

80% Completed

0% Completed

80% Completed

80% Completed

80% Completed

80% Completed

80% Completed

90% Completed

90% Completed

90% Completed

90% Completed

90% Completed

90% Completed

80% Completed

80% Completed

13 L.C.C work    
14 Grill & Railing work Apartment =A1

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =B1

Apartment =B3

Apartment =B4

Apartment =A5

Apartment =B6

Apartment =B7

Apartment =C1

Apartment =C2

Apartment =C3

Apartment =C4

Apartment =C5

Apartment =C6

Apartment =C7

Apartment =C8

 

60% Completed

80% Completed

80% Completed

80% Completed

80% Completed

80% Completed

40% Completed

60% Completed

60% Completed

60% Completed

60% Completed

60% Completed

40% Completed

80% Completed

80% Completed

80% Completed

80% Completed

80% Completed

80% Completed

80% Completed

15 Inside paint & Polishing work Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =B3

Apartment =B4

Apartment =A5

Apartment =B6

Apartment =B7

Apartment =C3

Apartment =C4

Apartment =C5

Apartment =C6

Apartment =C7

Apartment =C8

 

30% Completed

30% Completed

30% Completed

30% Completed

30% Completed

20% Completed

20% Completed

20% Completed

20% Completed

20% Completed

25% Completed

25% Completed

25% Completed

25% Completed

25% Completed

25% Completed

16 Switch -Socket fitting work    
17 Outside paint work   Ongoing
18 Door shutter work    
19 Aluminum work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =B1

Apartment =C1

Apartment =C2

Apartment =C3

Apartment =C4

Apartment =C5

Apartment =C6

Apartment =C7

Apartment =C8

 

20% Completed

20% Completed

20% Completed

20% Completed

20%  Completed

20% Completed

20% Completed

20% Completed

20% Completed

20% Completed

20% Completed

20% Completed

20% Completed

20% Completed

20% Completed

20% Completed

20 Tiles Pointing work & Marble finishing work    
21 Commode – Basin fitting work and C.P fittings work    
22 Lift/Generator /Substation /Solar work    
23 Boundary wall /Ground floor development work   70%
24 Roof top finishing work   10%
25 Roof top Gardening work G.F Garden work   40%