Southern Breeze

Bashundhara R/A, Dhaka

Completion Date

May 2024

Status Updated

March, 2024

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 100% completed
  Block work A-1=100%,B-1=100%C-1=100%,A-2=100%,    A-3=100%,A-4=100%                  A-5=100%,A-6=100%,A-7=100%, A-8 DUPLEX=100%,A8-SINGLE FLAT=100%
  Electrical  conduit work A-1=100%,B-1=100%C-1=100%,A-2=100%,    A-3=100%,A-4=100%                  A-5=100%,A-6=100%,A-7=100%, A-8 DUPLEX=100%,A8-SINGLE FLAT=100%
  Door frame fitting work A-1=100%,B-1=100%C-1=100%,A-2=100%,    A-3=100%,A-4=100%                  A-5=100%,A-6=100%,A-7=100%, A-8 DUPLEX=100%,A8-SINGLE FLAT=100%
  Sanitary & plumbing line  work A-1=100%,B-1=100%C-1=100%,A-2=100%,    A-3=100%,A-4=100%                  A-5=100%,A-6=100%,A-7=100%, A-8 DUPLEX=100%,A8-SINGLE FLAT=100%
  In side Plastering work A-1=100%,B-1=100%C-1=100%,A-2=100%,    A-3=100%,A-4=100%                  A-5=100%,A-6=100%,A-7=100%, A-8 DUPLEX=100%,A8-SINGLE FLAT=100%
  Electrical cable wiring work A-1=100%,B-1=100%C-1=100%,A-2=100%,    A-3=100%,A-4=100%                  A-5=100%,A-6=100%,A-7=100%, A-8 DUPLEX=100%,A8-SINGLE FLAT=100%
  Wall tiles  work A-1=100%,B-1=100%C-1=100%,A-2=100%,    A-3=100%,A-4=100%                  A-5=100%,A-6=100%,A-7=100%, A-8 DUPLEX=100%,A8-SINGLE FLAT=100%
  Common sanitary & Plumbing line work 100%
  Outside plastering work 100%
  Floor tiles/Marble work A-1=100%,B-1=100%C-1=100%,A-2=100%,    A-3=100%,A-4=100%                  A-5=100%,A-6=100%,A-7=100%, A-8 DUPLEX=100%,A8-SINGLE FLAT=100%
  Tiles Work common Area 90%
  L.C.C Work 100%
  Grill & Railing work A-1=100%,B-1=100%C-1=100%,A-2=100%,    A-3=100%,A-4=100%                  A-5=100%,A-6=100%,A-7=100%, A-8 DUPLEX=100%,A8-SINGLE FLAT=100%
  Grill Work Common 90%
  Inside paint & Polishing work 80%
  Switch -Socket fitting work 80%
  Outside paint work 70%
  Door shutter work 85%
  Aluminum/Glazing work 90%
  Tiles Pointing work & Marble finishing work 50%
  Commode – Basin fitting work and C.P fittings work 70%
  Lift/Generator /Substation /Solar work 60%
  Boundary wall /Ground floor development work 70%
  Roof top finishing work 90%
  Roof top Gardening work 87%