Completion Date
May 2024
Status Updated
March, 2024
SL. No | Name of the work | Progress details |
Foundation work | 100% Completed | |
Super Structure work | 100% completed | |
Block work | A-1=100%,B-1=100%C-1=100%,A-2=100%, A-3=100%,A-4=100% A-5=100%,A-6=100%,A-7=100%, A-8 DUPLEX=100%,A8-SINGLE FLAT=100% | |
Electrical conduit work | A-1=100%,B-1=100%C-1=100%,A-2=100%, A-3=100%,A-4=100% A-5=100%,A-6=100%,A-7=100%, A-8 DUPLEX=100%,A8-SINGLE FLAT=100% | |
Door frame fitting work | A-1=100%,B-1=100%C-1=100%,A-2=100%, A-3=100%,A-4=100% A-5=100%,A-6=100%,A-7=100%, A-8 DUPLEX=100%,A8-SINGLE FLAT=100% | |
Sanitary & plumbing line work | A-1=100%,B-1=100%C-1=100%,A-2=100%, A-3=100%,A-4=100% A-5=100%,A-6=100%,A-7=100%, A-8 DUPLEX=100%,A8-SINGLE FLAT=100% | |
In side Plastering work | A-1=100%,B-1=100%C-1=100%,A-2=100%, A-3=100%,A-4=100% A-5=100%,A-6=100%,A-7=100%, A-8 DUPLEX=100%,A8-SINGLE FLAT=100% | |
Electrical cable wiring work | A-1=100%,B-1=100%C-1=100%,A-2=100%, A-3=100%,A-4=100% A-5=100%,A-6=100%,A-7=100%, A-8 DUPLEX=100%,A8-SINGLE FLAT=100% | |
Wall tiles work | A-1=100%,B-1=100%C-1=100%,A-2=100%, A-3=100%,A-4=100% A-5=100%,A-6=100%,A-7=100%, A-8 DUPLEX=100%,A8-SINGLE FLAT=100% | |
Common sanitary & Plumbing line work | 100% | |
Outside plastering work | 100% | |
Floor tiles/Marble work | A-1=100%,B-1=100%C-1=100%,A-2=100%, A-3=100%,A-4=100% A-5=100%,A-6=100%,A-7=100%, A-8 DUPLEX=100%,A8-SINGLE FLAT=100% | |
Tiles Work common Area | 90% | |
L.C.C Work | 100% | |
Grill & Railing work | A-1=100%,B-1=100%C-1=100%,A-2=100%, A-3=100%,A-4=100% A-5=100%,A-6=100%,A-7=100%, A-8 DUPLEX=100%,A8-SINGLE FLAT=100% | |
Grill Work Common | 90% | |
Inside paint & Polishing work | 80% | |
Switch -Socket fitting work | 80% | |
Outside paint work | 70% | |
Door shutter work | 85% | |
Aluminum/Glazing work | 90% | |
Tiles Pointing work & Marble finishing work | 50% | |
Commode – Basin fitting work and C.P fittings work | 70% | |
Lift/Generator /Substation /Solar work | 60% | |
Boundary wall /Ground floor development work | 70% | |
Roof top finishing work | 90% | |
Roof top Gardening work | 87% |