Three

Gulshan, Dhaka

Completion Date

March 2023

Status Updated

February, 2023

SL. No Name of the work Progress details
01 Foundation work 100%  completed
02 Super Structure work 16th floor parapet RCC work 100%, OHWT RCC work 100% complete. `
03 Block Work 2nd floor 100%, 3rd floor 100%, 4th floor 100%, 5th floor 95 %,  6th  floor 95 %, 7th floor 100%, 8th floor 100%, 9th Floor 95% 10th floor 100%, 11th floor 100 %,& 12th 100%, 13th floor 9100%, & 14th floor 100 %, 15th floor 100%
04 Electrical  conduiting work    All floor 95 %
05 Door frame fitting work A2-100%, A3-100%, A4-100%, A5- 100%, A6- 100%, A7- 100%, A8- 100 %, A9- 100%, A10 -100 %, A11- 100%, A12-100%, A13-100%, A14-100%, A15-100%
06 Sanitary & plumbing line work. A2-100%, A3-100%, A4-100%, A5- 70%, A6- 70%, A7- 100%, A8- 85 %, A9- 70%, A10 -00 %, A11- 100%, A12-100%, A13-100%, A14-100%, A15-100%. Vertical Duct pipe 100% done.
07 In side Plastering work A2- 95 %, A3-95%, A4-95%, A5-90 %, A6-95 %, A7-95%,A8-95 %, A9-95%,  A10-90%,  A11-95%,  A12-95 %,  A13- 95%. & A14 -95%.A15-95% done.
08 Electrical cable wiring work  A2-90%, A3-90%, A4-90%,A5-80%, A6-00%, A7-90%,A8-90%, A9-70%, A10-00%, A11-90%, A12-90%, A13-90%, A14-90%, A15-90% done,
09 Wall tiles  work A2-100%, A3-100%, A4-50%,A5-60%, A6-90%, A7-95%,A8-90%, A9-80%, A10-00%, A11-90%, A12-90%, A13-100%, A14-100%, A15-100% done,
10 Common sanitary & Plumbing line work 75%
11 Outside plastering ()work 95%
12 Floor tiles/Marble work A2-100%, A3-100%, A4-60%,A5-90%, A6-90%, A7-95%,A8-90%, A9-100%, A10-00%, A11-100%, A12-90%, A13-100%, A14-100%, A15-100% done,
13 L.C.C work 100%
14 Grill & Railing work 85% done
15 Inside paint & Polishing work Onging
16 Switch -Socket fitting work  
17 Outside paint work  
18 Door shutter work  
19 Aluminum/Glazing work 10% done
20 Tiles Pointing work & Marble finishing work  
21 Commode – Basin fitting work and C.P fittings work  
22 Lift/Generator /Substation /Solar work 80%
23 Boundary wall /Ground floor development work 90%

 

24 Roof top finishing work 60%
25 Roof top Gardening work  