Silver Creek

Banani, Dhaka

Expected Completion Date

July 2024

Status Updated

July, 2024

SL. No Name of the work Progress details
01 Foundation work Foundation work 100% complete.

 

02 Super Structure work Ground floor to Roof top column casting 100% complete.

 

03 Block Work First floor to 9th floor blocks 100% complete.

Ground floor block work 100% complete.

 

04 Electrical conduite work 1st floor to 9th floor conduit work 100% Complete.
05 Door frame fitting work 1st floor to 9th floor 100% door frame fitting Complete.

 

06 Sanitary & plumbingline work 1st floor to 9th floor 100% complete.

 

 

07 In side Plastering work 1st floor to 9th floor plaster 100% complete.
08 Electrical cable wiring work 1st floor to 9th floor cable wiring 100% complete.
09 Wall tiles work 1st floor to 9th floor 100% complete

 

 

10 Common sanitary & Plumbing line work 100% complete.
11 Outside plastering work 1st floor to 9th floor plaster 100% complete.
12 Floor tiles/Marble work 1st floor to 9th floor 100% complete.

 

L.C.C work L.C.C work 100% complete.
14 Grill & Railing work 1st floor to 9th floor 100% complete.

 

 

15 Inside paint & Polishing work 1st floor to 9th floor 100% complete.

 

 

16 Switch -Socket fitting work 1st floor to 2nd floor 100% complete.

 

 

17 Outside paint work 1st floor to 9th floor outside paint work 100% complete.

 

18 Door shutter work 1st floor to 9th floor door shutter work 100% complete

 

19 Aluminum/Glazing work 1st floor to 9th floor aluminum work 100% complete

 

20 Tiles Pointing work & Marble finishing work 1st floor to 9th floor pointing work 100% complete.

 

 

21 Commode – Basin fitting work and C.P fittings work 1st floor to 9th floor pointing work 100% complete
22 Lift/Generator /Substation /Solar work Lift/Generator /Substation /Solar work 100% complete.
23 Boundary wall /Ground floor development work Ground Floor development work 100% complete.

False Celling development work 100 % complete.

 

24 Roof top finishing work Roof top finishing work 100% complete.
25 Roof top Gardening work Roof top gardening work 100% complete.