Moonwake

Dhanmondi, Dhaka

Completion Date

November 2024

Status Updated

March, 2024

SL. No Name of the work Progress details
1 Supper structure  13th floor roof slab 100%. Roof top- OHWT 100%, Parapet 80%, swimming pool 100%.
2 Ceiling plaster 2nd floor 100%, 3rd floor 100%, 4th floor 100%, 5th floor 100%, 6th floor 100%, 7th floor 100%. 8th floor 100 %. 9th floor 100%. 10th floor 100%. 11 th floor 100%, 12 th floor 100%.
3 Block work A2- 100%,B-2 100 %,C2-100%, A3-100%.B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B-100%, C6- 100%. A7- 100%, B7 100%.C7-100%. A8 100%, B8 100% C8 100%. A9 100%,B9 100%,C9 100%.A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%  C13- 100%.
  Wall plaster A2 90 %, B2- 90%, C2-90%, A3- 90%, B3-90%, C3-90%, A4-90%, B4-90%, C4-90%,A5-90%. B5 90%, C5 90%. A6-90%< B6-90%, C6-90%,A7-90%,B7- 90 %, C7-90%, A8-70%, B8-70%, C8-70%, A9 -95%, B9 95%, C9 95%, A10 95%, B10  95%, C 10 95%, A11-90%, B11-90%, C11-90%, A12-90%, B12-90%, C12-90%, B13-90%, C13-70%
4 Electrical  conducting work A2 90 %, B2- 90%, C2-90%, A3- 90%, B3-90%, C3-90%, A4-90%, B4-90%, C4-90%,A5-90%. B5 90%, C5 90%. A6-90%< B6-90%, C6-90%,A7-90%,B7- 90 %, C7-90%, A8-70%, B8-70%, C8-70%, A9 -95%, B9 95%, C9 95%, A10 95%, B10  95%, C 10 95%, A11-90%, B11-90%, C11-90%, A12-90%, B12-90%, C12-90%, B13-90%, C13-70%
5 Door frame fitting work A2 90 %, B2- 90%, C2-90%, A3- 90%, B3-90%, C3-90%, A4-90%, B4-90%, C4-90%,A5-90%. B5 90%, C5 90%. A6-90%< B6-90%, C6-90%,A7-90%,B7- 90 %, C7-90%, A8-70%, B8-70%, C8-70%, A9 -95%, B9 95%, C9 95%, A10 95%, B10  95%, C 10 95%, A11-90%, B11-90%, C11-90%, A12-90%, B12-90%, C12-90%, B13-90%, C13-70%
6 Sanitary & plumbing ( INTERNAL WIRING) A2 90 %, B2- 90%, C2-90%, A3- 90%, B3-90%, C3-90%, A4-90%, B4-90%, C4-90%,A5-90%. B5 90%, C5 90%. A6-90%< B6-90%, C6-90%,A7-90%,B7- 90 %, C7-90%, A8-70%, B8-70%, C8-70%, A9 -95%, B9 95%, C9 95%, A10 95%, B10  95%, C 10 95%, A11-90%, B11-90%, C11-90%, A12-90%, B12-90%, C12-90%, B13-90%, C13-70%
8 Electrical cable wiring work A2 90 %, C2-90%, A4-90%, B4-90%, C4-90%, C6-90%, , C8-90%, A10 90%, C 10 90%,  C12-90%,
9 Wall tiles  work A2 45 %, C2-45%, B3-70%, C3-70%, A4-45%, C4-70%,B5 70%, C5 70%. A6-20%, B6-10%, C6-70%,A7-50%,B7- 25 %, B8-10%, C8-70%, A9 -70%, B9 40%, C9 70%, A10 20 %, B10 10%,  B11-70%, C12-70%,
10 Common sanitary & Plumbing line work 20% (Only2 no’s concealed duct Complete).
  Outside plastering work 70%
  Floor tiles/Marble work C4-70%,C6-70%, C8-70%,
  L.C.C work  
  Grill & Railing work  
  Inside paint & Polishing work  
  Switch -Socket fitting work  
  Outside paint work  
  Door shutter work  
  Aluminum/Glazing work  
  Tiles Pointing work & Marble finishing work  
  Commode – Basin fitting work and C.P fittings work  

 

  Lift/Generator /Substation /Solar work  
  Boundary wall /Ground floor development work  
  Roof top finishing work  
  Roof top Gardening work  