Completion Date
November 2024
Status Updated
March, 2024
SL. No | Name of the work | Progress details |
1 | Supper structure | 13th floor roof slab 100%. Roof top- OHWT 100%, Parapet 80%, swimming pool 100%. |
2 | Ceiling plaster | 2nd floor 100%, 3rd floor 100%, 4th floor 100%, 5th floor 100%, 6th floor 100%, 7th floor 100%. 8th floor 100 %. 9th floor 100%. 10th floor 100%. 11 th floor 100%, 12 th floor 100%. |
3 | Block work | A2- 100%,B-2 100 %,C2-100%, A3-100%.B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B-100%, C6- 100%. A7- 100%, B7 100%.C7-100%. A8 100%, B8 100% C8 100%. A9 100%,B9 100%,C9 100%.A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100% C13- 100%. |
Wall plaster | A2 90 %, B2- 90%, C2-90%, A3- 90%, B3-90%, C3-90%, A4-90%, B4-90%, C4-90%,A5-90%. B5 90%, C5 90%. A6-90%< B6-90%, C6-90%,A7-90%,B7- 90 %, C7-90%, A8-70%, B8-70%, C8-70%, A9 -95%, B9 95%, C9 95%, A10 95%, B10 95%, C 10 95%, A11-90%, B11-90%, C11-90%, A12-90%, B12-90%, C12-90%, B13-90%, C13-70% | |
4 | Electrical conducting work | A2 90 %, B2- 90%, C2-90%, A3- 90%, B3-90%, C3-90%, A4-90%, B4-90%, C4-90%,A5-90%. B5 90%, C5 90%. A6-90%< B6-90%, C6-90%,A7-90%,B7- 90 %, C7-90%, A8-70%, B8-70%, C8-70%, A9 -95%, B9 95%, C9 95%, A10 95%, B10 95%, C 10 95%, A11-90%, B11-90%, C11-90%, A12-90%, B12-90%, C12-90%, B13-90%, C13-70% |
5 | Door frame fitting work | A2 90 %, B2- 90%, C2-90%, A3- 90%, B3-90%, C3-90%, A4-90%, B4-90%, C4-90%,A5-90%. B5 90%, C5 90%. A6-90%< B6-90%, C6-90%,A7-90%,B7- 90 %, C7-90%, A8-70%, B8-70%, C8-70%, A9 -95%, B9 95%, C9 95%, A10 95%, B10 95%, C 10 95%, A11-90%, B11-90%, C11-90%, A12-90%, B12-90%, C12-90%, B13-90%, C13-70% |
6 | Sanitary & plumbing ( INTERNAL WIRING) | A2 90 %, B2- 90%, C2-90%, A3- 90%, B3-90%, C3-90%, A4-90%, B4-90%, C4-90%,A5-90%. B5 90%, C5 90%. A6-90%< B6-90%, C6-90%,A7-90%,B7- 90 %, C7-90%, A8-70%, B8-70%, C8-70%, A9 -95%, B9 95%, C9 95%, A10 95%, B10 95%, C 10 95%, A11-90%, B11-90%, C11-90%, A12-90%, B12-90%, C12-90%, B13-90%, C13-70% |
8 | Electrical cable wiring work | A2 90 %, C2-90%, A4-90%, B4-90%, C4-90%, C6-90%, , C8-90%, A10 90%, C 10 90%, C12-90%, |
9 | Wall tiles work | A2 45 %, C2-45%, B3-70%, C3-70%, A4-45%, C4-70%,B5 70%, C5 70%. A6-20%, B6-10%, C6-70%,A7-50%,B7- 25 %, B8-10%, C8-70%, A9 -70%, B9 40%, C9 70%, A10 20 %, B10 10%, B11-70%, C12-70%, |
10 | Common sanitary & Plumbing line work | 20% (Only2 no’s concealed duct Complete). |
Outside plastering work | 70% | |
Floor tiles/Marble work | C4-70%,C6-70%, C8-70%, | |
L.C.C work | ||
Grill & Railing work | ||
Inside paint & Polishing work | ||
Switch -Socket fitting work | ||
Outside paint work | ||
Door shutter work | ||
Aluminum/Glazing work | ||
Tiles Pointing work & Marble finishing work | ||
Commode – Basin fitting work and C.P fittings work |
|
|
Lift/Generator /Substation /Solar work | ||
Boundary wall /Ground floor development work | ||
Roof top finishing work | ||
Roof top Gardening work |
16604