Moonwake

Dhanmondi, Dhaka

Expected Completion Date

December 2024

Status Updated

November, 2024

SL. No Name of the work Progress details
1 Supper structure  100% DONE
2 Ceiling plaster 2nd to 13th floor 100%
3 Block work 2nd to 13th floor 100%
  Wall plaster A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B-100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%  C13- 70 %.
4 Electrical  conducting work A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B-100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%  C13- 70 %.
5 Door frame fitting work A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B-100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%  C13- 70 %.
6 Sanitary & plumbing ( INTERNAL WIRING) A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B-100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%  C13- 70 %.
8 Electrical cable wiring work A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B-100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%  C13- 70 %.
9 Wall tiles work A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B-100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100% .
10 Sanitary & Plumbing  VERTICAL line work 95%
11 Outside plastering work 100%
12 Floor tiles/Marble work A2- 90%, B-2 100 %, C2-90%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B-100%, C6- 90%. A7- 90%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 90%, B11 100%, C11 90%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100% .
13 Facing Bricks (Outside) 90% done.
14

 

L.C.C work  
15 Grill & Railing work A2-90%,C2-90%, A3=100% B3-90%, C3-90%, A4-100%, B4-90%, C4-90%,  A5-100%,  B5- 90%, C-5  90%, A6-90%, B6-90% C6-90%,A7-100%, B7-90%, C7- 90%, A8-100%, B8-90%, C8-90%, A9-100%, B9-90%,C9-90%, A10-100%,B10-90%, C10-90%, A11-90%, B11-100%, C11-90% A12-100%, B12-90%, C12- 90%, A13-70%,  B13-70%.

 

16 Inside paint & Polishing work 1ST COAT=C2-90%,  B3-90%, C3-90%, A4- 90%, B4-90%, C4-90%,  A5-90%,  B5- 90%, C-5  90%, A6-90%, B6-90% C6-90%,A7-90%, B7-90%, C7- 90%, A8-90%, B8-90%, C8-90%, A9-90%, C9-90%, A10-90%, B10-90%, C10-90%, A11-90%, B11-100%, C11-90% A12-90%, B12-90%, C12- 90%, ,  B13-90%.

 

17 Switch -Socket fitting work  
18 Outside paint work PUUTY-70%
19 Door shutter work C4- 50%, A5-50%, B-50%, A6-50%. B6- 50%, C6-50%.A8 50%, B8 50% ,C8-50%. A10-50%, B10 50%, C10 50%, A11 90%,  A12-50%, B12-50%, C12 50%,
20 Aluminum/Glazing work  
20 Tiles Pointing work & Marble finishing work  
21 Commode – Basin fitting work and C.P fittings work  

 

22 Lift/Generator /Substation /Solar work Substation & Generator supply done.
23 Boundary wall /Ground floor development work 80% done.
24 Roof top finishing work  
25 Roof top Gardening work  

16604