The Millennial

Bhatara, Dhaka

Expected Completion Date

November 2025

Status Updated

November, 2024

SL. No Name of the work Progress details
1 Foundation work 100% completed
2 Basement work 100 % completed
3 Super Structure work 99 % completed (Tower-1, 8th floor roof completed, Tower-2, Roof casting completed and tower-3, Roof casting completed.)
4 Block Work Tower -01,

A-1 =100%, A-2= 100%, A-3= 100%, A-4=100%, A-5=100%, A-6=100%, A-7=100%, A-8 =100%,

Tower -02,

B-1=100%, B-2=100%, B-3 =100%, B-4=100%, B-5= 100%, B-6= 100%,  B-7= 100%, B-8= 100%,B-9= 100%, B-10= 100%, B-11= 100%, B-12= 100%, B-13=100% , B-14=100% , C-1= 100%,  C-2=100%, C-3 =100% , C-4= 100%, C-5=100% ,C-6= 100%, C-7= 100%, C-8= 100% , C-9= 100% ,C-10= 100%,  C-11= 100% , C-12= 100, C-13=100%   , C-14=100% ,  D-2=100% , D-3=100% , D-4=100% , D-5=100%. D-6= 100%, D-7= 100%, D-8= 100%, D-9= 100%, D-10= 100%, D-11= 100%, D-12= 100%, D-13=100%, D-14=100%, E-1= 100%, E-2 = 100%, E-3=100%, E-4=100%, E-5=100%, E-6= 100%, E-7= 100%, E-8= 100%, E-9= 100%, E-10= 100%, E-11= 100%, E-12= 100%, E-13=100% E-14=100%

Tower -03  

F-2= 100%, F-3= 100%, F-4=100%, F-5=100%, F-6=100%,  F-7=100%, F-8 = 100% , F-9 = 100% F-10= 100% F-11 = 100% ,F-12 = 100%,  F-13 = 100% ,  F-14 = 100%  .G-1=100%, G-2=100%, G-4=100%, G-5= 100%, G-6= 100%, G-7=100%, G-8= 100%,  G-9 = 100% ,G-10= 100% ,G-11 = 100%, G-12 = 100%, G-13 = 100%,  G-14 =100 0%,  H-1=100%, H-2=100%, H-3 =100% , H-4= 100%, H-5=100% , H-6 =100% , H-7= 100%, H-8=100% , H-9 = 100% ,H-10= 100% ,H-11 = 100%, H-12 = 100%, H-13 =100%, H-14 =100%, I-1=100% I-2=100% , I-3=100% , I-4=100% , I-5=100%.  I-6 =100%, I-7=100%, I-8=100%, I-9=100%, I-10=100%,

5 Electrical conduiting work Over all 90 % completed
6 Door frame fitting work Over all 80 % completed
7 Sanitary & plumbing line work Internal wiring 80% complete.
8 Inside Plastering work Overall 95%
9 Electrical cable wiring work 25 apartments complete.
10 Wall tiles work Wall tile: Tower -1, 95% T-2: 50%. T-3: 50% complete.
11 Common sanitary & Plumbing line work NYS
12 Outside plastering work Tower -1 completed. Tower-2= 90% T-3 = 40%
13 Floor tiles/Marble work Tower- 1, complete. Tower-2, = 20 % complete.
14 L.C.C work NYS
15 Grill & Railing work Tower- 1 = 80 % complete, Tower-2 = 30% complete, Tower-3 = 10% complete.
16 Inside paint & Polishing work Tower-1, Putty work =80% complete.
17 Switch -Socket fitting work NYS
18 Outside paint work NYS
19 Door shutter work NYS
20 Aluminum work NYS
21 Tiles Pointing work & Marble finishing work NYS
22 Commode – Basin fitting work and C.P fittings work NYS
23 Lift/Generator /Substation /Solar work NYS
24 Boundary wall /Ground floor development work 30% completed (Boundary wall 80% completed)
25 Roof top finishing work NYS
26 Roof top Gardening work G.F Garden work NYS
27 Land escape /Logo work NYS

 