Expected Completion Date
November 2026
Status Updated
January, 2026
| Name of the work | Progress details |
| Foundation work | 100% Completed |
| Super Structure work | 95% completed |
| Block work | A Type =100%
B Type =98% C Type =95% D Type =100% E Type =98% F Type =100% G Type =98% H Type =95% I Type =100% J Type =95% K Type =100% |
| Conduit Pipe Work | A Type =100%
B Type =100% C Type =100% D Type =100% E Type =100% F Type =100% G Type =100% H Type =90% I Type =100% J Type =100% K Type =100% |
| Door frame fitting work | A Type =98%
B Type =98% C Type =95% D Type =100% E Type =90% F Type =100% G Type =100% H Type =95% I Type =98% J Type =70% K Type =95% |
| Sanitary & plumbing line work | A Type =90%
B Type =90% C Type =80% D Type =90% E Type =60% F Type =100% G Type =100% H Type =80% I Type =80% J Type =50% K Type =90% |
| In side Plastering work | Tower1&2, Basement Ceiling=95%
GF Ceiling= 95%, 1st Floor Ceiling= 95%, 2nd Floor Ceiling= 95% 3rd Floor Ceiling=95%, 4th Floor Ceiling=95%, 5th Floor Ceiling=95%, 6th Floor Ceiling=95%, 7th Floor Ceiling=95%, 8th Floor Ceiling=95%, 9th Floor Ceiling=95%, 10th Floor Ceiling=95%, 11th Floor Ceiling=95%, 12th Floor Ceiling=95%, 13th Floor Ceiling=95%, Inside Wall Plaster: 1st floor 90%, 2nd floor 95% 3rd floor 95% 4th floor 95% 5th floor 95% 6th floor 90% 7th floor 90% 8th floor 80% 9th floor 70% 10th floor 40% 11th floor 20% 12th floor 10% 13th floor 40%
|
| Electrical cable wiring work | Basement= 95%,
Ground Floor=60% 1st floor 10%, 2nd floor 10% 3rd floor 80% 4th floor 10% 5th floor 10% 6th floor 10% 7th floor 10% 8th floor 10% 9th floor 10% 10th floor 10% 11th floor 10% 12th floor 05% 13th floor 05%
|
| Wall tiles work | Wall tiles work
1st floor 40%, 2nd floor 80% 3rd floor 80% 4th floor 80% 5th floor 80% 6th floor 80% 7th floor 80% 8th floor 80% 9th floor 80% 10th floor 80% 11th floor 80% 12th floor 50% 13th floor 50%
|
| Common sanitary & Plumbing line work | 1st Floor = 40%,
2nd Floor = 40% 3rd Floor = 40%, 4th Floor = 40%, 5th Floor = 40%, 6th Floor = 40%, 7th floor 10% 8th floor 10% 9th floor 10% 10th floor 10% 11th floor 10% 12th floor 05% 13th floor 05%
|
| Outside plastering work | Outside Wall Plaster:
13th floor 30% 12th floor 30% 11th floor 30% 10th floor 30% 09th floor 30% 08th floor 30% 07th floor 30% 06th floor 30% 05th floor 20% 04th floor 20% 03th floor 20% 02th floor 20% 01th floor 20%
|
| Floor tiles/Marble work/Granait work | Floor tiles work:
1st floor 7%, 2nd floor 7% 3rd floor 7% 4th floor 7% 5th floor 7% 6th floor 7% 7th floor 7% 8th floor 7% 9th floor 2% 10th floor 2% 11th floor 2% 12th floor 2% 13th floor 2%
Granait work: 1st floor 4%, 2nd floor 4% 3rd floor 4% 4th floor 4% 5th floor 4% 6th floor 4%
|
| L.C.C work | N/A |
| Grill & Railing work | N/A |
| Inside paint & Polishing work | N/A |
| Switch -Socket fitting work | N/A |
| Outside paint work | N/A |
| Door shutter work | N/A |
| Aluminum/Glazing work | N/A |
| Tiles Pointing work & Marble finishing work | N/A |
| Commode – Basin fitting work and C.P fittings work | N/A |
| Lift/Generator /Substation /Solar work | N/A |
| Boundary wall /Ground floor development work | Boundary wall = 60%
|
| Roof top finishing work | N/A |
| Roof top Gardening work | N/A |