Welcome Home

Mirpur, Dhaka

Expected Completion Date

November 2026

Status Updated

November, 2025

Name of the work Progress details
Foundation work 100% Completed
Super Structure work 95% completed
Block work A Type =98%

B Type =98%

C Type =95%

D Type =98%

E Type =90%

F Type =98%

G Type =95%

H Type =85%

I Type =85%

J Type =80%

K Type =98%

Conduit Pipe Work A Type =90%

B Type =90%

C Type =75%

D Type =80%

E Type =75%

F Type =80%

G Type =70%

H Type =70%

I Type =70%

J Type =70%

K Type =90%

Door frame fitting work A Type =95%

B Type =95%

C Type =80%

D Type =90%

E Type =85%

F Type =95%

G Type =90%

H Type =60%

I Type =60%

J Type =60%

K Type =95%

Sanitary & plumbing line work A Type =50%

B Type =50%

C Type =50%

D Type =50%

E Type =50%

F Type =50%

G Type =50%

H Type =50%

I Type =50%

J Type =50%

K Type =50%

In side Plastering work Tower1&2, Basement Ceiling=95%

GF Ceiling= 95%,

1st Floor Ceiling= 95%,

2nd Floor Ceiling= 95%

3rd Floor Ceiling=95%,

4th Floor Ceiling=95%,

5th Floor Ceiling=95%,

6th Floor Ceiling=95%,

7th Floor Ceiling=95%,

8th Floor Ceiling=95%,

9th Floor Ceiling=95%,

10th Floor Ceiling=95%,

11th Floor Ceiling=95%,

12th Floor Ceiling=95%,

13th Floor Ceiling=95%,

Inside Wall Plaster:

1st floor 90%,

2nd floor 95%

3rd floor 95%

4th floor 95%

5th floor 95%

6th floor 80%

7th floor 80%

8th floor 60%

9th floor 50%

10th floor 20%

11th floor 05%

Electrical cable wiring work Basement= 95%,

Ground Floor=60%

1st floor 10%,

2nd floor 10%

3rd floor 10%

4th floor 10%

5th floor 10%

6th floor 10%

7th floor 10%

8th floor 10%

9th floor 10%

Wall tiles work Wall tiles work

1st floor 35%,

2nd floor 55%

3rd floor 55%

4th floor 45%

5th floor 35%

6th floor 45%

7th floor 35%

8th floor 45%

9th floor 35%

Common sanitary & Plumbing line work 1st Floor = 40%,

2nd Floor = 40%

3rd Floor = 40%,

4th Floor = 40%,

5th Floor = 40%,

6th Floor = 40%,

Outside plastering work Outside Wall Plaster:

13th floor 5%

12th floor 5%

11th floor 5%

10th floor 5%

09th floor 5%

08th floor 5%

07th floor 5%

06th floor 5%

05th floor 5%

04th floor 5%

Floor tiles/Marble work N/A
L.C.C work N/A
Grill & Railing work N/A
Inside paint & Polishing work N/A
Switch -Socket fitting work N/A
Outside paint work N/A
Door shutter work N/A
Aluminum/Glazing work N/A
Tiles Pointing work & Marble finishing work N/A
Commode – Basin fitting work and C.P fittings work N/A
Lift/Generator /Substation /Solar work N/A
Boundary wall /Ground floor development work Boundary wall = 55%

 

Roof top finishing work N/A
Roof top Gardening work N/A