Expected Completion Date
November 2026
Status Updated
November, 2025
| Name of the work | Progress details |
| Foundation work | 100% Completed |
| Super Structure work | 95% completed |
| Block work | A Type =98%
B Type =98% C Type =95% D Type =98% E Type =90% F Type =98% G Type =95% H Type =85% I Type =85% J Type =80% K Type =98% |
| Conduit Pipe Work | A Type =90%
B Type =90% C Type =75% D Type =80% E Type =75% F Type =80% G Type =70% H Type =70% I Type =70% J Type =70% K Type =90% |
| Door frame fitting work | A Type =95%
B Type =95% C Type =80% D Type =90% E Type =85% F Type =95% G Type =90% H Type =60% I Type =60% J Type =60% K Type =95% |
| Sanitary & plumbing line work | A Type =50%
B Type =50% C Type =50% D Type =50% E Type =50% F Type =50% G Type =50% H Type =50% I Type =50% J Type =50% K Type =50% |
| In side Plastering work | Tower1&2, Basement Ceiling=95%
GF Ceiling= 95%, 1st Floor Ceiling= 95%, 2nd Floor Ceiling= 95% 3rd Floor Ceiling=95%, 4th Floor Ceiling=95%, 5th Floor Ceiling=95%, 6th Floor Ceiling=95%, 7th Floor Ceiling=95%, 8th Floor Ceiling=95%, 9th Floor Ceiling=95%, 10th Floor Ceiling=95%, 11th Floor Ceiling=95%, 12th Floor Ceiling=95%, 13th Floor Ceiling=95%, Inside Wall Plaster: 1st floor 90%, 2nd floor 95% 3rd floor 95% 4th floor 95% 5th floor 95% 6th floor 80% 7th floor 80% 8th floor 60% 9th floor 50% 10th floor 20% 11th floor 05% |
| Electrical cable wiring work | Basement= 95%,
Ground Floor=60% 1st floor 10%, 2nd floor 10% 3rd floor 10% 4th floor 10% 5th floor 10% 6th floor 10% 7th floor 10% 8th floor 10% 9th floor 10% |
| Wall tiles work | Wall tiles work
1st floor 35%, 2nd floor 55% 3rd floor 55% 4th floor 45% 5th floor 35% 6th floor 45% 7th floor 35% 8th floor 45% 9th floor 35% |
| Common sanitary & Plumbing line work | 1st Floor = 40%,
2nd Floor = 40% 3rd Floor = 40%, 4th Floor = 40%, 5th Floor = 40%, 6th Floor = 40%, |
| Outside plastering work | Outside Wall Plaster:
13th floor 5% 12th floor 5% 11th floor 5% 10th floor 5% 09th floor 5% 08th floor 5% 07th floor 5% 06th floor 5% 05th floor 5% 04th floor 5% |
| Floor tiles/Marble work | N/A |
| L.C.C work | N/A |
| Grill & Railing work | N/A |
| Inside paint & Polishing work | N/A |
| Switch -Socket fitting work | N/A |
| Outside paint work | N/A |
| Door shutter work | N/A |
| Aluminum/Glazing work | N/A |
| Tiles Pointing work & Marble finishing work | N/A |
| Commode – Basin fitting work and C.P fittings work | N/A |
| Lift/Generator /Substation /Solar work | N/A |
| Boundary wall /Ground floor development work | Boundary wall = 55%
|
| Roof top finishing work | N/A |
| Roof top Gardening work | N/A |