Expected Completion Date
March 2025
Status Updated
March, 2025
| SL. No | Name of the work | Progress details |
| Foundation work | 100% Completed | |
| Super Structure work | 100% completed | |
| Block work | All flat 100% Complete, Common area 100% Complete. | |
| Electrical conduit work | All flat 100% Complete, Common area 100% Complete | |
| Door frame fitting work | All flat 100% Complete, Common area 100% Complete | |
| Sanitary & plumbing line work | Internal Sanitary & Plumbing work all flat 100% Complete | |
| In side Plastering work | All flat 100% Complete, Common area 99% Complete | |
| Electrical cable wiring work | All flat 100% Complete, Common area 99% Complete | |
| Wall tiles work | All flat 100% Completed, Common area 100% Complete | |
| Common sanitary & Plumbing line work | 98% completed | |
| Outside plastering work | 100% completed | |
| Floor tiles/Marble work | 100% Completed | |
| L.C.C work | 100% Completed | |
| Grill & Railing work | 99% Completed | |
| Inside paint & Polishing work | 99% Completed | |
| Switch -Socket fitting work | 99% Completed | |
| Outside paint work | 90% Completed | |
| Door shutter work | 100% Completed | |
| Aluminum/Glazing work | 99% Completed | |
| Tiles Pointing work & Marble finishing work | 94% Completed | |
| Commode – Basin fitting work and C.P fittings work | 95% Completed | |
| Lift/Generator /Substation /Solar work | 90% Completed | |
| Boundary wall /Ground floor development work | 95% Completed | |
| Roof top finishing work | 98% Completed | |
| Roof top Gardening work | 40% Completed |