Completion Date
November 2025
Status Updated
April, 2024
SL. No | Name of the work | Progress details |
1 | Foundation work | 100% Completed. |
2 | Basement work | 100% Completed. |
3 | Super Structure work | 80% completed. (T-1- 5F roof Completed, T-2 – 7F roof Completed. T-3 – 10F roof Completed, T-4 – 10F Roof Completed) |
4 | Block Work | 60 % completed. |
5 | Electrical conduiting work | 55% Completed. |
6 | Door frame fitting work | 50% Completed. |
7 | Sanitary & plumbing line work | 45% Completed. |
8 | Inside Plastering work | 45% Completed. |
9 | Electrical cable wiring work | 10% Completed. |
10 | Wall tiles work | nill |
11 | Common sanitary & Plumbing line work | nill |
12 | Outside plastering work | 10% Completed. |
13 | Floor tiles/Marble work | nill |
14 | L.C.C work | nill |
15 | Grill & Railing work | nill |
16 | Inside paint & Polishing work | nill |
17 | Switch -Socket fitting work | nill |
18 | Outside paint work | nill |
19 | Door shutter work | nill |
20 | Aluminum work | nill |
21 | Tiles Pointing work & Marble finishing work | nill |
22 | Commode – Basin fitting work and C.P fittings work | nill |
23 | Lift/Generator /Substation /Solar work | nill |
24 | Boundary wall /Ground floor development work | 65% Completed. |
25 | Roof top finishing work | nill |
26 | Roof top Gardening work G.F Garden work | nill |
27 | Land escape /Logo work | nill |
16604