Expected Completion Date
November 2024
Status Updated
November, 2024
SL. No | Name of the work | Progress details |
1 | Foundation work | 100% completed. |
2 | Basement work | N/A |
3 | Super Structure work | 100% completed (8th Floor Roof slab casting completed) |
4 | Block Work | 100% completed |
5 | Electrical conduiting work | 98% completed |
6 | Door frame fitting work | 100% completed |
7 | Sanitary & plumbing line work | 98% completed
|
8 | Inside Plastering work | 100% completed |
9 | Electrical cable wiring work | 98% completed |
10 | Wall tiles work | 98% Completed |
11 | Common sanitary & Plumbing line work | 70% |
12 | Outside plastering work | 98% Completed |
13 | Floor tiles/Marble work | 98% Completed |
14 | L.C.C work | 100 % Completed |
15 | Grill & Railing work | 98% |
16 | Inside paint & Polishing work | 85% |
17 | Switch -Socket fitting work | 80% |
18 | Outside paint work | 70% |
19 | Door shutter work | 85% |
20 | Aluminum work | 80% |
21 | Tiles Pointing work & Marble finishing work | 80% |
22 | Commode – Basin fitting work and C.P fittings work | 70% Completed |
23 | Lift/Generator /Substation /Solar work | 60% |
24 | Boundary wall /Ground floor development work | 60% |
25 | Roof top finishing work | 85% |
26 | Roof top Gardening work G.F Garden work | 70% |
27 | Land escape /Logo work | NYS |