Completion Date
May 2025
Status Updated
April, 2024
11 | Outside plastering work | Apartment =A7
Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Apartment =A10 Apartment =B10 Apartment =A11 Apartment =B11 Apartment =A12 Apartment =B12
|
20% Complete
20% Complete 20% Complete 20% Complete 20% Complete 20% Complete 20% Complete 20% Complete 20% Complete 20% Complete 20% Complete 20% Complete |
|
12 | Floor tiles/Marble work | |||
13 | L.C.C work | |||
14 | Grill & Railing work | |||
15 | Inside paint & Polishing work | |||
16 | Switch -Socket fitting work | |||
17 | Outside paint work | |||
18 | Door shutter work | |||
19 | Aluminum work | |||
20 | Tiles Pointing work & Marble finishing work | |||
21 | Commode – Basin fitting work and C.P fittings work | |||
22 | Lift/Generator /Substation /Solar work | |||
23 | Boundary wall /Ground floor development work | 10% Complete | ||
24 | Roof top finishing work | |||
25 | Roof top Gardening work G.F Garden work |
16604