Zenith

Aftabnagar, Dhaka

Completion Date

May 2025

Status Updated

April, 2024

11 Outside plastering work Apartment =A7

Apartment =B7

Apartment =A8

Apartment =B8

Apartment =A9

Apartment =B9

Apartment =A10

Apartment =B10

Apartment =A11

Apartment =B11

Apartment =A12

Apartment =B12

 

 

20% Complete

20% Complete

20% Complete

20% Complete

20% Complete

20% Complete

20% Complete

20% Complete

20% Complete

20% Complete

20% Complete

20% Complete

12 Floor tiles/Marble work
13 L.C.C work
14 Grill & Railing work
15 Inside paint & Polishing work
16 Switch -Socket fitting work
17 Outside paint work
18 Door shutter work
19 Aluminum work
20 Tiles Pointing work & Marble finishing work
21 Commode – Basin fitting work and C.P fittings work
22 Lift/Generator /Substation /Solar work
23 Boundary wall /Ground floor development work 10% Complete
24 Roof top finishing work
25 Roof top Gardening work G.F Garden work

16604