New Horizon

Purana Paltan, Dhaka

Expected Completion Date

December 2024

Status Updated

November, 2024

SL. No Name of the work Progress details

 

Remark
01 Foundation work 100% completed.  
02 Super Structure work 100% completed.  
03  

 

Block Work

Basement=100%

G. F.=60%

A1= 100%, A2= 100%, A3= 100%, A4= 100%,

A5=100%, B5=100%,

A6=100%, B6=100%,

A7=100%, B7=100%,

A8=100%, B8=100%,

Roof= 100%

 
04  

 

Electrical Conducting work

Basement=60%

G. F=50%

A1= 100%, A2= 100%, A3= 100%, A4= 100%,

A5=100%, B5=100%,

A6=100%, B6=100%,

A7=100%, B7=100%,

A8=100%, B8=100%,

Roof = 100%

 
05  

 

Door frame fitting work

Basement=100%

G. F=100%

 

A1= 100%, A2= 100%, A3= 100%, A4= 100%,

A5=100%, B5=100%,

A6=100%, B6=100%,

A7=100%, B7=100%,

A8=100%, B8=100%

 
06  

 

Sanitary & plumbing line work

Basement=20%

G. F=30%

A1= 100%, A2= 100%, A3= 100%, A4= 100%,

A5=100%, B5=100%,

A6=100%, B6=100%,

A7=100%, B7=100%,

A8=100%, B8=100%,

 
07  

 

In side Plastering work

Basement=80%

G. F=60%

A1= 100%, A2= 100%, A3= 100%, A4= 100%,

A5=100%, B5=100%,

A6=100%, B6=100%,

A7=100%, B7=100%,

A8=100%, B8=100%,

 
08  

 

Electrical cable wiring work

Basement=60%

G, F=30%

A1= 95%, A2= 95%, A3= 75%, A4= 95%,

A5=90%, B5=90%,

A6=90%, B6=90%,

A7=90%, B7=90%,

A8=90%, B8=90%,

 
09  

 

Wall Tiles work

Basement=0% G, F=0%

A1= 90%, A2= 90%, A3= 90%, A4= 90%,

A5=90%, B5=90%,

A6=90%, B6=90%,

A7=90%, B7=90%,

A8=90%, B8=90%,

 
10  

 

Common sanitary & Plumbing line work

Basement=20%

G, F=30%

A1= 80%, A2= 80%, A3= 80%, A4= 80%,

A5=80%, B5=80%,

A6=80%, B6=80%,

A7=80%, B7=80%,

A8=80%, B8=80%,

 
11 Outside plastering work 95% Completed  
12  

 

Floor tiles/Marble work

Basement=0%

G, F=0%

A1= 90%, A2= 90%, A3= 90%, A4= 90%,

A5=90%, B5=90%,

A6=90%, B6=90%,

A7=90%, B7=90%,

A8=90%, B8=90%,

 
13 L.C.C work 25% Completed  
14 Grill & Railing work 90 % Completed  
15 Inside paint & Polishing work 50 % Completed  
16 Switch -Socket fitting work 5 % Completed  
17 Outside paint work 30 % Completed  
18 Door shutter work 15 % Completed  
19 Aluminum work 30 % Completed  
20 Tiles Pointing work & Marble finishing work 25 % Completed  
21 Commode – Basin fitting work and C.P fittings work 15 % Completed  
22 Lift/Generator /Substation /Solar work 75% Completed  
23 Boundary wall /Ground floor development work 75% Completed  
24 Roof top finishing work 80% Completed  
25 Roof top Gardening work G.F Garden work 45% Completed  