The Palms

Aftabnagar, Dhaka

Expected Completion Date

January 2025

Status Updated

November, 2024

SL. No Name of the work Location Progress details Remarks
01 Foundation work   100% completed.  
02 Super Structure work   100%  
03 Block Work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 
04 Electrical conduiting work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 

 
05 Door frame fitting work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 
06 Sanitary & plumbing line work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

 

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 
07 In side Plastering work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 

 
08 Electrical cable wiring work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

 

 100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 

 
09 Wall tiles work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 

 
10 Common sanitary & Plumbing line work   95%Complete

 

 
11 Outside plastering work   100% Complete  
12 Floor tiles/Marble work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

100% Complete

100% Complete

100%Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 

 

 
13 L.C.C work    

100%

 

 
14 Grill & Railing work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

100%

100%

100%

100%

100%

100%

100%

100%

100%

 
15 Inside paint & Polishing work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

85%

85%

85%

85%

85%

85%

85%

85%

85%

 

 
16 Switch -Socket fitting work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

100%

100%

100%

100%

100%

100%

100%

100%

100%

 

 
17 Outside paint work   50%  
18 Door shutter work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

100%

100%

100%

100%

100%

100%

100%

100%

100%

 

 
19 Aluminum work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

90%

90%

90%

90%

90%

90%

90%

90%

90%

 

 
20 Tiles Pointing work & Marble finishing work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

0%

0%

100%

20%

20%

20%

20%

20%

0%

 

 
21 Commode – Basin fitting work and C.P fittings work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Apartment =A9

0%

0%

80%

0%

0%

0%

0%

0%

0%

 

 
22 Lift/Generator /Substation /Solar work   85%  
23 Boundary wall /Ground floor development work   98%Complete  
24 Roof top finishing work   98%Complete  
25 Roof top Gardening work G.F Garden work   80%  