Aqualuna

Dhanmondi, Dhaka

Expected Completion Date

October 2025

Status Updated

January, 2026

SL. No Name of the work Progress details
01 I-Jost drive Complete,
02 Earth cutting Complete,
03 Mat casting Complete,
04 Supper structure 1)Basement Retaining wall,Column+Share wall casting,Basement Roof Slab Casting Complete,

2)Ground Floor Column+Share wall Casting Complete,

3)Ground Floor Roof slab(1st floor slab-Mezzanine part) Casting Complete,

4) )1st Floor Column+Share wall Casting Complete

5)2nd Floor slab Casting work complete.

6)2nd Floor Colunm casting Complete.

7)3rd Floor Slab Casting Work Complete,

8)3rd Floor Column Casting Work Complete,

9) 4th Floor Slab Casting Work Complete,

10) 4th Floor Column Casting Work Complete,

11)5th Floor Slab Casting Work Complete,

12)5th Floor Column Casting  work Complete,

13)6th Floor Slab Casting Work Complete,

14)6th Floor Column Casting Complete,

15)7th Floor Slab Casting Complete.

16)7th Floor Column Casting Complete,

17) 8th Floor Slab Casting Complete,

18) 8th Floor Column Casting Complete,

19) ) 9th Floor Slab Casting Complete,

20) 10th Floor Slab Casting Complete,

21) 10th Floor Column Casting Complete,

22)11th Floor Slab Casting Work complete,

23) 11th Floor Column Casting 100% Complete,

24)11th Floor Roof Slab Casting Work Complete.

25) Above Roof Top Floor Column Casting 80% Complete,

26)OHWT -1,Bottom Slab+ Wall Casting Complete,

27)Above Roof Swimming Pool Bottom Slab Shutter Work  Complete,

28)Above Roof Swimming Pool Wall Casting 100%Complete,

29)Above Roof Swimming Pool,Deck Floor Slab Casting 100%Complete,

30)Above Roof Swimming Pool, Deck Slab,OHWT Top Slab Casting 100%Complete,

31)Out Side Fin Wall Casting 100% Complete,

 

05 Electrical  conducting work 1)Basement Roof slab PVC Pipe Conduit Work Complete,

2) Ground Floor Roof slab/1st Floor Slab(Mezzanine part) PVC Pipe Conduit work Complete,

3) 2nd Floor slab PVC Pipe Conduit work Complete.

4)3rd Floor slab PVC Pipe Conduit work Complete,

5) 4th Floor slab PVC Pipe Conduit work Complete,

6) 5th Floor slab PVC Pipe Conduit work Complete,

7) 6th Floor slab PVC Pipe Conduit work Complete,

8) 7th Floor slab PVC Pipe Conduit work Complete,

9) 8th Floor slab PVC Pipe Conduit work Complete,

10) 9th Floor slab PVC Pipe Conduit work Complete.

11) 10th Floor slab PVC Pipe Conduit work Complete.

12) 11th Floor slab PVC Pipe Conduit work Complete,

13) 12th Floor slab(Roof of 11th Floor) PVC Pipe Conduit work Complete,

 

14)3rd to 8th Floor Internal W/G Pipe+ MK Box  Work 98%

Complete,

15)2nd+9th Floor Internal W/G Pipe+ MK Box  Work 98%

Complete,

16)10th Floor Internal W/G Pipe+ MK Box  Work 98%

Complete,

17)11th Floor Internal W/G Pipe + MK Box  Work 98%

Complete,

 

06 Door frame fitting work 1)2nd  to 8th Floor Door frame fitting work 100%Complete.

2)9th to 10th Floor Door frame fitting work 100%Complete.

 

07 Sanitary & plumbing line  work(Ace drain water line, ver – vertical line) 1) 2nd Floor slab Verandah Upvc Pipe Conduit work Complete.

2)3rd Floor slab Verandah Upvc Pipe Conduit work Complete,

3) 4th Floor slab Verandah Upvc Pipe Conduit work Complete,

4) 5th Floor slab Verandah Upvc Pipe Conduit work Complete,

5) 6th Floor slab Verandah Upvc Pipe Conduit work Complete.

6) 7th Floor slab Verandah Upvc Pipe Conduit work Complete,

7) 8th Floor slab Verandah Upvc Pipe Conduit work Complete,

8) 9th Floor slab Verandah Upvc Pipe Conduit work Complete

9) 10th Floor slab Verandah Upvc Pipe Conduit work Complete,

10) 11th Floor slab Verandah Upvc Pipe Conduit work Complete,

11)All Floor Sanitary Duct Vertical Upvc Line Complete,

12)5th Floor PPR Pipe Wairing 98%Complete,

13)7th Floor PPR Pipe Wairing 98%Complete,

14)9th Floor PPR Pipe Wairing 98%Complete,

15)2nd,7th & 11th Floor PPR Pipe Wairing Work 98%Complete.

 

08 In side Plastering work 1)Basement Ceiling Plaster Work complete,

2)1st Floor Ceiling Plaster Work Complete

3)2nd Floor Ceiling Plaster WorkComplete,

4) 3rd Floor Ceiling Plaster Work Complete,

5)4th Floor Ceiling Plaster Work Complete

6) 5th Floor Ceiling Plaster Work Complete.

7)6th Floor Ceiling Plaster Work Complete.

8)7th Floor Ceiling Plaster Work Complete.

9) 8th Floor Ceiling Plaster Work Complete,

10) 9th Floor Ceiling Plaster Work Complete,

11) 10th Floor Ceiling Plaster Work Complete,

12)Basement Wall Plaster Work complete,

13) 2nd Floor Internal Plaster Work Complete

14)3rd Floor Internal Plaster Work Complete

15)4th Floor Internal Plaster Work Complete,

16)5th,6th,7th,9th Floor Internal Plaster Work Complete,

17) 10th Floor Internal Plaster Work Complete,

18)11th Floor Internal Plaster Work Complete,

19) G/Floor Internal Plaster Work 95%Complete,

 

09 Electrical cable wiring work 1)Basement Ceiling Cable Wiring Work complete.

2)5th+6th Floor Cable Wiring Work complete.

3)10th& 11th Floor Cable Wairing Work Complete.

4)2nd+3rd Floor Cable Wiring Work complete.

 

10  Inside Panel slab Fitting  work 1)2nd Floor Panel wall Fitting Work 100% Complete,

2) 3rd Floor Panel wall Fitting Work 100% Complete,

3) 4th Floor Panel wall Fitting Work 100% Complete,

4)5th Floor Panel wall Fitting Work 100% Complete.

5)6th Floor Panel wall Fitting Work 100% Complete.

6)7th Floor Panel wall Fitting Work 100% Complete

7)8th Floor Panel wall Fitting Work 100% Complete

8) 9th Floor Panel wall Fitting Work 100% Complete,

9) 10th Floor Panel wall Fitting Work 100% Complete,

10) 11th Floor Panel wall Fitting Work 100% Complete,

 

11 Common sanitary & Plumbing line work Basement High Level  Pipe Work 100% Complete.
12 Outside plastering work 1)North Out Side Plaster Work 100% Complete,

2)East Out Side Plaster Work 100% Complete,

3)West Out Side Plaster Work 100% Complete,

4) Front Out Side Plaster Work 100% Complete,

 

 

13 Wall/Floor tiles/Marble work 1) 2nd Floor Bath wall+ Genaral Floor Tiles 95% Complete,

2) 3rd Floor Wall + Genaral Floor Tiles 100% Complete,

3)5th Floor(B5) Wall + Genaral Floor Tiles 100% Complete,

4) 5th Floor(A5) Wall +Genaral Floor Tiles 100% Complete,

5) 6th Floor Genaral Floor Marble Complete

6)7th Floor Wall +Genaral Floor Tiles 95% Complete,

7)10th Floor Genaral Floor Tiles 100% Complete,

8)11th Floor Bath wall+ Genaral Floor Tiles 100% Complete,

9)Fire Stair Tiles Complete,

10) Main Stair Tiles 100% Complete,

11)Swimming Pool Tiles Complete

14 L.C.C work  
15 Grill & Railing work 1)2nd Floor Fixed+Sliding Grill Fitting 100% Complete,

2) 3rd Floor F+Sliding -Grill Fitting 100% Complete,

4th Floor F+Sliding -Grill Fitting 100% Complete,

3) ) 5th Floor F+Sliding -Grill Fitting 100% Complete

4)6th Floor F+Sliding Grill Fitting 100% Complete

5)7th Floor F+Sliding Grill Fitting 95% Complete

6)8th Floor F+Sliding Grill Fitting Complete

7)9th Floor F+Sliding Grill Fitting Complete

8)10th Floor F+Sliding Grill Fitting Complete

9)11th Floor F+Sliding Grill Fitting Complete

 

16 Inside paint & Polishing work 1)1st to Above Floor Paint Work30% Complete,

2)Basement to G/Floor Paint Work 30% Complete,

3) All Stair-Lobby Paint 30% Complete,

17 Switch -Socket fitting work  
18 Outside paint work  
19 Door shutter work 1)5th Floor Door Shutter Fitting 50% Complete
20 Aluminum/Glazing work 1)All Floor Thai-Aluminium Framing Work 80% Complete,
21 Tiles Pointing work & Marble finishing work 1)2nd to 11th Floor Wall Tiles Pointing Work 70% Complete,
22 Commode – Basin fitting work and C.P fittings work  

 

23 Lift/Generator /Substation /Solar work Generator /Substation /Solar work Setting Complete, Lift Ongoing
24 Boundary wall /Ground floor development work 1)G/Floor Boundary B/ Wall Work 100% Complete,
25 Roof top finishing work Roof top Tlies Finishing Work 80% Complete,
26 Roof top Gardening work  

 