The Retreat

Bashundhara R/A, Dhaka

Expected Completion Date

March 2025

Status Updated

October, 2024

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 100% completed
  Block work 100% Complete
  Electrical  conduit work  99% Complete
  Door frame fitting work 100% Complete
  Sanitary & plumbing line  work 95%  Complete
  In side Plastering work 99% Complete
  Electrical cable wiring work 90% Complete
  Wall tiles  work 92% Complete
  Common sanitary & Plumbing line work 85% Complete
  Outside plastering work 98% Complete
  Floor tiles/Marble work 91% Complete
  L.C.C work 100% Complete
  Grill & Railing work 90% Complete
  Inside paint & Polishing work 40%
  Switch -Socket fitting work N/A
  Outside paint work N/A
  Door shutter work N/A
  Aluminum/Glazing work 20%
  Tiles Pointing work & Marble finishing work N/A
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work 30%
  Boundary wall /Ground floor development work 20%
  Roof top finishing work 40%
  Roof top Gardening work N/A