Gold Star

Block K, Bashundhara R/A

Expected Completion Date

September 2025

Status Updated

September, 2025

SL. No Name of the work Location Progress details Remarks
01 Foundation work   100% completed.  
02 Super Structure work   100%  
03 Block Work Community Hall

Apartment =A2

Apartment =C2

Apartment =D2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment =A8

Apartment =B8

Apartment =A9

Apartment =B9

Roof Top

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 

 
04 Electrical conduiting work Community Hall

Apartment =A2

Apartment =C2

Apartment =D2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment =A8

Apartment =B8

Apartment =A9

Apartment =B9

Roof Top

 

99% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

98% Complete

 
05 Door frame fitting work Community Hall

Apartment =A2

Apartment =C2

Apartment =D2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment =A8

Apartment =B8

Apartment =A9

Apartment =B9

Roof top

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 

 
06 Sanitary & plumbing line work Community Hall

Apartment =A2

Apartment =C2

Apartment =D2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment =A8

Apartment =B8

Apartment =A9

Apartment =B9

Roof top

96% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

95% Complete

 

 
07 In side Plastering work Community Hall

Apartment =A2

Apartment =C2

Apartment =D2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment =A8

Apartment =B8

Apartment =A9

Apartment =B9

Roof top

 

 

100 % Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

99% Complete

 

 
08 Electrical cable wiring work  

Community Hall

Apartment =A2

Apartment =C2

Apartment =D2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment =A8

Apartment =B8

Apartment =A9

Apartment =B9

Roof top

 

98% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

90% Complete

 

 
09 Wall tiles work  

Community Hall

Apartment =A2

Apartment =C2

Apartment =D2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment =A8

Apartment =B8

Apartment =A9

Apartment =B9

Roof top

 

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

96% Complete

 

 
10 Common sanitary & Plumbing line work   90%

 

 
11 Outside plastering work   100% Complete  
12 Floor tiles/Marble work   100%

 

 
13 L.C.C work   100%  
14 Grill & Railing work   100%  
15 Inside paint & Polishing work   100%  
16 Switch -Socket fitting work   100%  
17 Outside paint work   20%  
18 Door shutter work   100%  
19 Aluminum work   95%  
20 Tiles Pointing work & Marble finishing work   98%  
21 Commode – Basin fitting work and C.P fittings work   95%  
22 Lift/Generator /Substation /Solar work   98%  
23 Boundary wall /Ground floor development work   92%  
24 Roof top finishing work   80%  
25 Roof top Gardening work G.F Garden work   70%  

 