Expected Completion Date
October 2024
Status Updated
November, 2024
SL. No | Name of the work | Progress details |
01 | Foundation work | 100 % completed. |
02 | Super Structure work | 100% completed. |
03 | Block Work | A-1 = 100% , A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%, |
04 | Electrical conducting work | A-1 = 100% , A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%, |
05 | Door frame fitting work | A-1 = 100% , A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8=100% |
06 | Sanitary & plumbing line work | A-1 = 100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100% |
07 | In side Plastering work | A-1 = 100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%, |
08 | Electrical cable wiring work | A-1 = 100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100% ,A-7= 100%, A-8= 100% |
09 | Wall tiles work | A-1 = 100% , A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%, |
10 | Common sanitary & Plumbing line work | 100% |
11 | Outside plastering work | 100% Completed |
12 | Floor tiles/Marble work | A-1 = 100% , A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%, |
13 | L.C.C work | 100% |
14 | Grill & Railing work | 100% |
15 | Inside paint & Polishing work | A-1 =80% , A-2= 80%, A-3= 80%, A-4= 80%, A-5= 80%, A-6= 80%, A-7=80%, A-8= 80%, |
16 | Switch -Socket fitting work | A-1 =80% , A-2= 80%, A-3= 80%, A-4= 80%, A-5= 80%, A-6= 80%, A-7=80%, A-8= 80%, |
17 | Outside paint work | 70% |
18 | Door shutter work | 100% |
19 | Aluminum work | 90% |
20 | Tiles Pointing work & Marble finishing work | 20% |
21 | Commode – Basin fitting work and C.P fittings work | 30% |
22 | Lift/Generator /Substation /Solar work | 80% |
23 | Boundary wall /Ground floor development work | 90% |
24 | Roof top finishing work | 90% |
25 | Roof top Gardening work G.F Garden work | 80% |