Green View

Mirpur, Dhaka

Expected Completion Date

December 2024

Status Updated

November, 2024

SL. No Name of the work Progress details
01 Foundation work 100% completed.
02 Super Structure work 100 % completed.
03 Block Work A-1 =100%, A-2= 100%, A-3= 100%, A-4=100, A-5=100%, B-1=100%, B-2=100%, B-3 =100%, B-4=100%, B-5= 100%, C-1=100%, C-2=100%, C-3 =100% , C-4= 100%, C-5=100% , D-1=100% D-2=100% , D-3=100% , D-4=100% , D-5=100%.  E-2 = 100%, E-3=100% , E-4=100%, E-5=100% ,
04 Electrical conducting work A-1 =100%, A-2= 100%, A-3= 100%, A-4=100, A-5=100%, B-1=100%, B-2=100%, B-3 =100% , B-4=100%, B-5= 100%, C-1=100%, C-2=100%, C-3 =100% , C-4= 100%, C-5=100% , D-1=100% D-2=100% , D-3=100% , D-4=100% , D-5=100%.  E-2 = 100%, E-3=100% , E-4=100%, E-5=100%
05 Door frame fitting work A-2= 100%, A-3= 100%, A-4=100, A-5=100%, B-2=100%, B-3 =100% , B-4=100%, B-5= 100%, C-1=100%, C-2=100%, C-3 =100% , D-1=100% D-2=100% , D-3=100% , D-4=100% , ,E-2 = 100%, E-3=100% , E-4=100%, ,
06 Sanitary & plumbing line work Over all 80%
07 In side Plastering work A-1 =100%, A-2= 100%, A-3= 100%, A-4=100, A-5=100%, B-1=100%, B-2=100%, B-3 =100% , B-4=100%, B-5= 100%, C-1=100%, C-2=100%, C-3 =100% , C-4= 100%, C-5=0% , D-1=100% D-2=100% , D-3=100% , D-4=100% , D-5=100%.  E-2 = 100%, E-3=100%, E-4=100%, E-5=100%
08 Electrical cable wiring work 100%
09 Wall tiles work Over all 100%
10 Common sanitary & Plumbing line work Over all 90%
11 Outside plastering work 100%
12 Floor tiles/Marble work 24 flat completed out of 24 (100%)
13 L.C.C work 100%
14 Grill & Railing work 100%
15 Inside paint & Polishing work 70%
16 Switch -Socket fitting work N/A
17 Outside paint work 50%
18 Door shutter work 100%
19 Aluminum work 60%
20 Tiles Pointing work & Marble finishing work 5%
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work 95%
24 Roof top finishing work 95%
25 Roof top Gardening work G.F Garden work 60%

 

16604