Completion Date
September 2024
Status Updated
April, 2024
SL. No | Name of the work | Progress details |
Foundation work | 100% Completed | |
Super Structure work | 100% completed | |
Block work | A-1=95%, A-2=95%, A-3= 95%, A-4=95%, A-5=95%, A-6=950%. | |
Electrical conduit work | A-1=90%, A-2=90%, A-3= 90%, A-4=90%, A-5=90%, A-6=90%. | |
Door frame fitting work | A-1=100%, A-2=100%, A-3=100%, A-4=100%, A-5=100%, A-6=100%. | |
Sanitary & plumbing line work | A-1=90%, A-2=90%, A-3= 90%, A-4=90%, A-5=90%, A-6=90%. | |
In side Plastering work | A-1=90%, A-2=90%, A-3= 70%, A-4=90%, A-5=90%, A-6=90%. | |
Electrical cable wiring work | A-1=30%, A-2=30%, A-3= 30%, A-4=30%, A-5=30%, A-6=30%. | |
Wall tiles work | A-1=70%, A-2=70%, A-3= 70%, A-4=70%, A-5=70%, A-6=70%. | |
Common sanitary & Plumbing line work | N/A | |
Outside plastering work | 70% | |
Floor tiles/Marble work | N/A | |
L.C.C work | N/A | |
Grill & Railing work | 10% | |
Inside paint & Polishing work | N/A | |
Switch -Socket fitting work | N/A | |
Aluminum/Glazing work | N/A | |
Outside paint work | N/A | |
Door shutter work | N/A | |
Tiles Pointing work & Marble finishing work | N/A | |
Commode – Basin fitting work and C.P fittings work | N/A | |
Lift/Generator /Substation /Solar work | N/A | |
Boundary wall /Ground floor development work | N/A | |
Roof top finishing work | N/A | |
Roof top Gardening work | N/A |