Expected Completion Date
July 2025
Status Updated
May, 2025
SL. No | Name of the work | Progress details |
Foundation work | 100% Completed | |
Super Structure work | 100% completed | |
Block work | A-2=100%, B-2=100%, A-3=100%, B-3=100%, A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%, A-8=100%, B-8=100%, A-9=100%, B-9=100% | |
Electrical conduit work | A-2=95%, B-2=95%, A-3=95%, B-3=95%, A-4=95%, B-4=95%, A-5=95%, B-5=95%, A-6=95%, B-6=95%, A-7=95%, B-7=95%,
A-8=95%, B-8=95%, A-9=95%, B-9=95%, |
|
Door frame fitting work | A-2=100%, B-2=100%, A-3=100%, B-3=100%, A-4=100%, B-4=100%, A-5=100%, B-5=100%, A-6=100%, B-6=100%, A-7=100%, B-7=100%,
A-8=100%, B-8=100%, A-9=100%, B-9=100%, |
|
Sanitary & plumbing line work | A-2=87%, B-2=87%, A-3=87%, B-3=87%, A-4=87%, B-4=87%, A-5=87%, B-5=87%, A-6=87%, B-6=87%, A-7=87%, B-7=87%, A-8=87%, B-8=87%, A-9=87%, B-9=87% | |
In side Plastering work | A-2=99%, B-2=99% A-3=99%, B-3=99%, A-4=99%, B-4=99%, A-5=99%, B-5=99%, A-6=99%, B-6=99%, A-7=99%, B-7=99%,
A-8=99%, B-8=99%, A-9=99%, B-9=99%, |
|
Electrical cable wiring work | A-2=97%, B-2=97%, A-3=97%, B-3=97%, A-4=97%, B-4=97%, A-5=97%, B-5=97%, A-6=97%, B-6=97%, A-7=97%, B-7=97%, A-8=97%, B-8=97%, A-9=97%, B-9=97% | |
Wall tiles work | A-2=65%, B-2=65%, A-3=80%, B-3=80%, A-4=80%, B-4=80%, A-5=80%, B-5=80%, A-6=80%, B-6=80%, A-7=80%, B-7=80%, A-8=80%, B-8=80%, A-9=80%, B-9=80% | |
Common sanitary & Plumbing line work | N/A | |
Outside plastering work | 01. North side = 100%,
02. South side = 100%, 03. East Side = 100%, 04. West Side = 100%. |
|
Floor tiles/Marble work | 80% | |
L.C.C work | 100% | |
Grill & Railing work | 70% | |
Inside paint & Polishing work | 10% | |
Switch -Socket fitting work | N/A | |
Aluminum/Glazing work | N/A | |
Outside paint work | 05% | |
Door shutter work | N/A | |
Tiles Pointing work & Marble finishing work | N/A | |
Commode – Basin fitting work and C.P fittings work | N/A | |
Lift/Generator /Substation /Solar work | N/A | |
Boundary wall /Ground floor development work | 60% | |
Roof top finishing work | 60% | |
Roof top Gardening work | 10% |