Expected Completion Date
February 2025
Status Updated
November, 2024
SL. No | Name of the work | Progress details |
01 | Foundation work | 100% |
02 | Super Structure work | 100% |
03 | Block Work | A-1 = 100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5=100%, A-6= 100%, A-7= 90% A-8= 100%,, |
04 | Electrical conducting work | A-1 = 100% , A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%, |
05 | Door frame fitting work | A-1 =100% , A-2= 100%, A-3= 100%, A-4= 100% ,A-5= 100% ,A-6= 100% ,A-7= 100% A-8= 100% |
06 | Sanitary & plumbing line work | A-1 =60% , A-2= 70%, A-3= 80%, A-4= 80% , A-5= 80%, A-6= 80%, A-7= 90%, A-8= 90% |
07 | In side Plastering work | A-1 =90% , A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100% A-6= 100% A-7= 100%, A-8= 100% |
08 | Electrical cable wiring work | Over all 90% |
09 | Wall tiles work | Over all100% |
10 | Common sanitary & Plumbing line work | N/A |
11 | Outside plastering work | 100% |
12 | Floor tiles/Marble work | A-1 =90% , A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100% A-6= 100% A-7= 100%, A-8= 100% |
13 | L.C.C work | 100% |
14 | Grill & Railing work | Over all 80% |
15 | Inside paint & Polishing work | 30% |
16 | Switch -Socket fitting work | N/A |
17 | Outside paint work | N/A |
18 | Door shutter work | N/A |
19 | Aluminum work | N/A |
20 | Tiles Pointing work & Marble finishing work | N/A |
21 | Commode – Basin fitting work and C.P fittings work | N/A |
22 | Lift/Generator /Substation /Solar work | 20% |
23 | Boundary wall /Ground floor development work | 50% |
24 | Roof top finishing work | 80% |
25 | Roof top Gardening work G.F Garden work | N/A |