The Skyline

Dhanmondi, Dhaka

Completion Date

May 2026

Status Updated

April, 2024

SL. No Name of the work Progress details
01 Shore pile 100%.
Tie beam 100%
02 Earth cutting 100%
03 Mat casting 100%
04 Supper structure Basement 2 Retaining wall and Roof Slab Casting 100% Complete.

Basement 1 Retaining wall and Roof Slab Casting 100% Complete.

Ground Floor Column and Slab Casting 100% Complete.

1st Floor column and Slab Casting 100% Complete.

2nd Floor Column & Slab casting 100% completed.

3rd Floor Column & Slab casting 100% completed.

4th Floor Column & Slab casting 100% completed.

5th Floor Column & Slab casting 100% completed.

6th Floor Column & Slab casting 100% completed.

7th Floor Column casting 100% completed.

7th floor roof slab shuttering & casting complete

1st & 2nd floor east side fair face wall casting 100% complete

3rd floor fair face wall casting 90% complete

1st & 2nd floor west side block work 80% complete.

1st,2nd,3rd,4th & 5th floor ceiling plaster average 90% complete.

05 Electrical conducting work
06 Door frame fitting work
07 Sanitary & plumbing line  work(Ace drain water line, ver- vertical line)
08 In side Plastering work
09 Electrical cable wiring work
10 Wall tiles  work
11 Common sanitary & Plumbing line work
12 Outside plastering work
13 Floor tiles/Marble work
14 L.C.C work
15 Grill & Railing work
16 Inside paint & Polishing work
17 Switch -Socket fitting work
18 Outside paint work
19 Door shutter work
20 Aluminum/Glazing work
21 Tiles Pointing work & Marble finishing work
22 Commode – Basin fitting work and C.P fittings work  

 

23 Lift/Generator /Substation /Solar work
24 Boundary wall /Ground floor development work
25 Roof top finishing work
26 Roof top Gardening work