The Skyline

Dhanmondi, Dhaka

Expected Completion Date

May 2026

Status Updated

March, 2026

SL. No Name of the work Progress details
01 Shore pile 100%.
  Tie beam 100%
02 Earth cutting 100%
03 Mat casting 100%
04 Supper structure Basement 2 Retaining wall and Roof Slab Casting 100% Complete.

Basement 1 Retaining wall and Roof Slab Casting 100% Complete.

Ground Floor Column and Slab Casting 100% Complete.

1. 1st Floor to 15th floor slab & Column casting  100% complete

2. 1st to 14th  floor north & south side fair face wall casting 100%     complete.

3. 1st to 15th floor ceiling plaster  100% complete.

4. 1st to 14th  floor block work average 100 % complete.

5. 1st to 14th floor stair  Ceiling plaster100 % complete   .

6. 1st to 14th floor False slab  & lintel casting average 100% complete

7. 14th,15th floor Up stand & planter box casting 100% complete

8. 1st to 14th floor SDB wall casting 100% complete

 

 

05

 

 

 

Panel work 1st floor to 13 th floor panel casting & fitting 100% completed
06 Electrical conduiting 1st to 14th floor vertical riser pipe 100% complete

1st to 14th floor internal 100% complete

07 Door frame fitting work 1st to 13th floor 100% complete
08 Sanitary & plumbing line work (Ac drain  line,  vertical line) G.floor to 13th Average 100% complete

 

09 In side Plastering work Basement -01, Basement-02 Retaining wall plaster100% complete

Typical floor ( 1st To 14th ) wall plaster 100%  complete

 

10 Electrical cable wiring work B2, B1, 1st   to 6th floor 100 %complete

7th to 14th floor 95% complete

11 Wall tiles work Kitchen  100% complete. Bath room 95% complete
12 Common sanitary & Plumbing line work 1st   to 14th floor  Internal wiring average 98% complete
13 Outside plastering work 100% work done
14 Floor tiles A1,A2 ,, A3,,A4,A5,A6,A7,A8,A9, A10,A11,A12,A13,B1, B2,B3,B4,B5,B6,B7,B8,B9,B10,B11,B12,B13Typical floor ( 1st To 14th ) total  100% complete.
15 Grill & Railing work( stair ) Stair railing fitting 97% complete
16 Inside paint & Polishing work 1st to 13th floor (1st coat) 100% complete.

1st to 8th floor (2nd coat) 95% complete

17 Switch -Socket fitting work 1st to 7th floor 95% complete
18 Outside paint work 1st to 14th floor 1st coat 100% complete
19 Door shutter work  
20 Aluminum/Glazing work Front side framing & Glass Fixing100 % complete And other side frame & glass fixing =95% complete.
21 Tiles Pointing work & Marble finishing work 1st & 5th floor 60 % complete
22 Commode – Basin fitting work and C.P fittings work 2nd to 13th floor kitchen sink fitting  100% complete
23 Lift/Generator /Substation /Solar work Lift work 70% complete. Generator work  60% complete
24 Boundary wall /Ground floor development work Grade beam & column casting 100% complete.

Boundary brick wall 100% complete, plaster work 100% complete.

25 Roof top finishing work  Water tank tiles work 100% finishing complete
26 Roof top Gardening work  R.C.C work 100% complete.