Expected Completion Date
August 2025
Status Updated
June, 2025
SL. No | Name of the work | Progress details |
Foundation work | 100% Completed | |
Super Structure work | 99% completed | |
Block work | A-1=100%,A-2=100%A-3=100%, A-4=100%,A-5=100% ,A-6 =100%,A-7=100%,A-8=100%. | |
Electrical conduit work | A-1=100%,A-2=100%A-3=100%, A-4=100%,A-5=100% ,A-6 =100%,A-7=100%,A-8=100%. | |
Door frame fitting work | A-1=100%,A-2=100%A-3=100%, A-4=100%,A-5=100% ,A-6 =100%,A-7=100%,A-8=100%. | |
Sanitary & plumbing line work | A-1=88%,A-2=88%A-3=88%, A-4=88%,A-5=88% ,A-6 =87%,A-7=88%,A-8=88%. | |
In side Plastering work | A-1=100%,A-2=100%A-3=100%, A-4=100%,A-5=100% ,A-6 =100%,A-7=100%,A-8=100%. | |
Electrical cable wiring work | A-1=100%,A-2=100%A-3=100%, A-4=100%,A-5=100% ,A-6 =100%,A-7=100%,A-8=100%. | |
Wall tiles work | 98% | |
Common sanitary & Plumbing line work | 82% | |
Outside plastering work | 100% | |
Floor tiles/Marble work | A-1=100%,A-2=100%A-3=100%, A-4=100%, A-5=100% ,A-6 =100%,A-7=100%,A-8=100%. | |
L.C.C work | 100% | |
Grill & Railing work | 85% | |
Inside paint & Polishing work | 65% | |
Switch -Socket fitting work | N/A | |
Outside paint work | 50% | |
Door shutter work | 100% | |
Aluminum/Glazing work | 83% | |
Tiles Pointing work & Marble finishing work | 20% | |
Commode – Basin fitting work and C.P fittings work | N/A | |
Lift/Generator /Substation /Solar work | 70% | |
Boundary wall /Ground floor development work | 80% | |
Roof top finishing work | 45% | |
Roof top Gardening work | 65% |