The Boulevard

Block A, Bashundhara R/A

Expected Completion Date

August 2025

Status Updated

June, 2025

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 99% completed
  Block work A-1=100%,A-2=100%A-3=100%, A-4=100%,A-5=100% ,A-6 =100%,A-7=100%,A-8=100%.
  Electrical  conduit work A-1=100%,A-2=100%A-3=100%, A-4=100%,A-5=100% ,A-6 =100%,A-7=100%,A-8=100%.
  Door frame fitting work A-1=100%,A-2=100%A-3=100%, A-4=100%,A-5=100% ,A-6 =100%,A-7=100%,A-8=100%.
  Sanitary & plumbing line  work A-1=88%,A-2=88%A-3=88%, A-4=88%,A-5=88% ,A-6 =87%,A-7=88%,A-8=88%.
  In side Plastering work A-1=100%,A-2=100%A-3=100%, A-4=100%,A-5=100% ,A-6 =100%,A-7=100%,A-8=100%.
  Electrical cable wiring work A-1=100%,A-2=100%A-3=100%, A-4=100%,A-5=100% ,A-6 =100%,A-7=100%,A-8=100%.
  Wall tiles  work 98%
  Common sanitary & Plumbing line work 82%
  Outside plastering work 100%
  Floor tiles/Marble work A-1=100%,A-2=100%A-3=100%, A-4=100%, A-5=100% ,A-6 =100%,A-7=100%,A-8=100%.
  L.C.C work 100%
  Grill & Railing work 85%
  Inside paint & Polishing work 65%
  Switch -Socket fitting work N/A
  Outside paint work 50%
  Door shutter work 100%
  Aluminum/Glazing work 83%
  Tiles Pointing work & Marble finishing work 20%
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work 70%
  Boundary wall /Ground floor development work 80%
  Roof top finishing work 45%
  Roof top Gardening work 65%

 