Expected Completion Date
December 2025
Status Updated
September, 2025
| SL. No | Name of the work | Location | Progress details | Remarks |
| 01 | Foundation work | 100% completed. | ||
| 02 | Super Structure work | 100% Completed | ||
| 03 | Block Work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9 |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete |
|
| 04 | Electrical conduiting work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9 |
90% Complete
90% Complete 90% Complete 90% Complete 90% Complete 90% Complete 90% Complete 90% Complete 90% Complete |
|
| 05 | Door frame fitting work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9 |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete |
|
| 06 | Sanitary and plumbing work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9 |
80%Complete
80%Complete 80%Complete 80%Complete 80%Complete 80%Complete 80%Complete 80%Complete 80%Complete |
|
| 07 | In side Plastering work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9
|
95%Complete
95%Complete 95%Complete 95%Complete 95%Complete 95%Complete 95%Complete 95%Complete 95%Complete
|
|
| 08 | Electrical cable wiring work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9
|
90%Complete
90%Complete 90%Complete 90%Complete 90%Complete 90%Complete 90%Complete 90%Complete 90%Complete
|
|
| 09 | Wall tiles work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9 |
85%Complete
85%Complete 90%Complete 95%Complete 95%Complete 95%Complete 95%Complete 40%Complete 90%Complete |
|
| 10 | Common sanitary & Plumbing line work |
|
||
| 11 | Outside plastering work | 95%Complete
|
||
| 12 | Floor tiles/Marble work | 80%Complete
|
||
| 13 | L.C.C work | 100%Complete
|
||
| 14 | Grill & Railing work | 65%Complete
|
||
| 15 | Inside paint & Polishing work | |||
| 16 | Switch -Socket fitting work | |||
| 17 | Outside paint work | |||
| 18 | Door shutter work | |||
| 19 | Aluminum work | |||
| 20 | Tiles Pointing work & Marble finishing work | |||
| 21 | Commode – Basin fitting work and C.P fittings work |
|
||
| 22 | Lift/Generator /Substation /Solar work | 85%Complete
|
||
| 23 | Boundary wall /Ground floor development work | 70%Complete
|
||
| 24 | Roof top finishing work | 40%Complete
|
||
| 25 | Roof top Gardening work G.F Garden work |