Spring Field

Bashundhara R/A, Dhaka

Completion Date

April 2025

Status Updated

April, 2024

SL. No Name of the work Progress details Remarks
01 Foundation work 100% Complete
02 Super Structure work 4th floor roof slab casting completed.
03 Block Work A2 Block work 10%

A3 Block work 5%

04 Electrical conduiting work
05 Door frame fitting work
06 Sanitary & plumbing line  work
07 In side Plastering work A2 celing plaster 100% complete

A3 celing plaster 20%

08 Electrical cable wiring work
09 Wall tiles  work
10 Common sanitary & Plumbing line work
11 Outside plastering work
12 Floor tiles/Marble work
13 L.C.C work
14 Grill & Railing work
15 Inside paint & Polishing work
16 Switch -Socket fitting work
17 Outside paint work
18 Door shutter work
19 Aluminum work
20 Tiles Pointing work & Marble finishing work
21 Commode – Basin fitting work and C.P fittings work
22 Lift/Generator /Substation /Solar work
23 Boundary wall /Ground floor development work
24 Roof top finishing work
25 Roof top Gardening work G.F Garden work