Spring Field

Bashundhara R/A, Dhaka

Expected Completion Date

August 2025

Status Updated

June, 2025

SL. No Name of the work Location Progress details Remarks
01 Foundation work   100% Complete  
02 Super Structure work   95% Compltete  
03 Block Work Apartment A1

Apartment A2

Apartment A3

Apartment A4

Apartment A5

Apartment A6

Apartment A7

Apartment A8

Apartment A9

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% complete

100% complete

 
04 Electrical conduiting work Apartment A1

Apartment A2

Apartment A3

Apartment A4

Apartment A5

Apartment A6

Apartment A7

Apartment A8

Apartment A9

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% complete

100% complete

 
05 Door frame fitting work Apartment A1

Apartment A2

Apartment A3

Apartment A4

Apartment A5

Apartment A6

Apartment A7 Apartment A8

Apartment A9

 

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% complete

100% complete

 
06 Sanitary & plumbing line  work   Vertical plumbing line 50%

Vertical ppr line            80%

Bathroom ppr wearing 90%

 
07 In side Plastering work Ground floor

Apartment A1

 

Apartment A2

 

Apartment A3

 

Apartment A4

 

Apartment A5

 

Apartment A6

 

Apartment A7

 

Apartment A8

 

Apartment A9

Celling 90% inside wall 50%

Celling 100% & Inside wall 100%

Celling 100% & Inside wall 100%

Celling 100% & Inside wall 100%

Celling 100% & Inside wall 100%

Celling 100%  & Inside wall 100%

Celling 100% & Inside wall 100%

Celing 100% & Inside wall 100%

Celing 100% Complete wall 100%

Celing 100% Complete wall 100%

 

 

 

 

 

 

08 Electrical cable wiring work Stair area

Apartment A2

Apartment A5

Apartment A4

Apartment A6

Apartment A7

Apartment A8

Apartment A9

100% Complete

100% Complete

100% Complete

100% complete

100% Complete

100%   Complete

100%   Complete

100%   Complete

 
09 Wall tiles  work Apartment A1

Apartment A2

Apartment A5

Apartment A6

Apartment A9

70% Complete

80% Complete

70% Complete

70% complete

70% complete

 
10 Common sanitary & Plumbing line work      
11 Outside plastering work   Out side plaster north complete 80%

Out side plaster east side 70%

Out side plaster west side 70%

 
12 Floor tiles/Marble work Apartment A6 85% complete  
13 L.C.C work      
14 Grill & Railing work      
15 Inside paint & Polishing work      
16 Switch -Socket fitting work      
17 Outside paint work      
18 Door shutter work      
19 Aluminum work      
20 Tiles Pointing work & Marble finishing work      
21 Commode – Basin fitting work and C.P fittings work      
22 Lift/Generator /Substation /Solar work      
23 Boundary wall /Ground floor development work      
24 Roof top finishing work      
25 Roof top Gardening work G.F Garden work      

 

16604