The Laurels

Uttara, Dhaka

Completion Date

July 2025

Status Updated

April, 2024

SL. No Name of the work Progress details
Foundation work 95% Completed
Super Structure work 65% completed
Block work 07% completed
Electrical  conduit work N/A
Door frame fitting work N/A
Sanitary & plumbing line  work N/A
In side Plastering work 7%
Electrical cable wiring work N/A
Wall tiles  work N/A
Common sanitary & Plumbing line work N/A
Outside plastering work N/A
Floor tiles/Marble work N/A
L.C.C work N/A
Grill & Railing work N/A
Inside paint & Polishing work N/A
Switch -Socket fitting work N/A
Outside paint work N/A
Door shutter work N/A
Aluminum/Glazing work N/A
Tiles Pointing work & Marble finishing work N/A
Commode – Basin fitting work and C.P fittings work N/A
Lift/Generator /Substation /Solar work N/A
Boundary wall /Ground floor development work N/A
Roof top finishing work N/A
Roof top Gardening work N/A