Chestnut

Block K, Bashundhara R/A

Expected Completion Date

March 2026

Status Updated

December, 2025

SL. No Name of the work Location Progress details Remarks
01 Foundation work   100% complete  
02 Super Structure work   100% Complete  
03 Block Work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 
04 Electrical conduiting work (Wall) Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 
05 Door frame fitting work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 
06 Sanitary & plumbing line work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

 

 
07 In side Plastering work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 

Wall plaster work
08 Electrical cable wiring work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

95% Complete

100% Complete

95% Complete

95% Complete

100% Complete

100% Complete

95% Complete

 
09 Wall tiles work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

98% Complete

95% Complete

95% Complete

90% Complete

95% Complete

95% Complete

95% Complete

 
10 Common sanitary & Plumbing line work   85% Complete  
11 Outside plastering work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

96% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 

 
12 Floor tiles/Marble work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

95% Com

95% Complete

95% Complete

90% Complete

95% Complete

95% Complete

95% Complete

 

 
13 L.C.C work   100% Complete

 

 
14 Grill & Railing work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

 
15 Inside paint & Polishing work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

   
16 Switch -Socket fitting work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

 

 

 
17 Outside paint work    5% Complete  
18 Door shutter work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

 

 

 
19 Aluminum work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

25% Complete

35% Complete

35% Complete

35% Complete

45% Complete

45% Complete

45% Complete

Thai Frame Fitting work.
20 Tiles Pointing work & Marble finishing work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

   
21 Commode – Basin fitting work and C.P fittings work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

   
22 Lift/Generator /Substation /Solar work   15% Complete  
23 Boundary wall /Ground floor development work   58% Complete  
24 Roof top finishing work   85% Complete  
25 Roof top Gardening work G.F Garden work      

16604