Expected Completion Date
October 2027
Status Updated
March, 2026
| SL. No | Name of the work | Progress details |
| 01 | Foundation work | Footing 100% completed, |
| 02 | Super Structure work | Up to 13th floor roof slab 100% done. OHWT RCC work 100%, Parapet wall 90 % done. Swimming pool RCC Work 90 % done |
| 03 | Block Work | A1- 10%, B1-10%, A2- 90%, B2-90%, A3-90%, B3-90%, A4-90%, B4-90%, A5-10%, B5-90%, A6-30 %, B6-90%, A7-90%, B7-90 %, A8 -80%, B8-80%, A9-80%, B9-80%, A10-70%, B10-70%, A11-10%, B11-10%, |
| 04 | Electrical conduiting work | A3-90%, B3-90%, A4-90%, B4-90%, A5-10%, B5-90%, A6-30 %, B6-90% |
| 05 | Door frame fitting work | A3-60%, B3-
60%, A4-50%, B4-50%, |
| 06 | Sanitary & plumbing line work. | Vertical duct (9 no’s) line 80% done |
| 07 | In side Plastering work | Ceiling plaster, Basement to 13th floor 85% complete. |
| 08 | Electrical cable wiring work | |
| 09 | Wall tiles work | |
| 10 | Common sanitary & Plumbing line work | |
| 11 | Outside plastering work | |
| 12 | Floor tiles/Marble work | |
| 13 | L.C.C work | |
| 14 | Grill & Railing work | |
| 15 | Inside paint & Polishing work | |
| 16 | Switch -Socket fitting work | |
| 17 | Outside paint work | |
| 18 | Door shutter work | |
| 19 | Aluminum/Glazing work | |
| 20 | Tiles Pointing work & Marble finishing work | |
| 21 | Commode – Basin fitting work and C.P fittings work | |
| 22 | Lift/Generator /Substation /Solar work | |
| 23 | Boundary wall /Ground floor development work | |
| 24 | Roof top finishing work | |
| 25 | Roof top Gardening work |