Expected Completion Date
April 2026
Status Updated
October, 2024
SL. No | Name of the work | Progress details |
01 | Foundation work | 100%, Basement roof slab casting completed. |
02 | Super Structure work | 25 % Completed. 1st floor roof slab casting completed. |
03 | Block Work | N/A |
04 | Electrical conducting work | N/A |
05 | Door frame fitting work | N/A |
06 | Sanitary & plumbing line work | N/A |
07 | In side Plastering work | N/A |
08 | Electrical cable wiring work | N/A |
09 | Wall tiles& floor tiles work | N/A
|
10 | Common sanitary & Plumbing line work | N/A |
11 | Outside plastering work | N/A |
12 | Floor tiles/Marble work | N/A |
13 | L.C.C work | N/A |
14 | Grill & Railing work | N/A |
15 | Inside paint & Polishing work | N/A |
16 | Switch -Socket fitting work | N/A |
17 | Outside paint work | N/A |
18 | Door shutter work | N/A |
19 | Aluminum/Glazing work | N/A |
20 | Tiles Pointing work & Marble finishing work | N/A |
21 | Commode – Basin fitting work and C.P fittings work | N/A |
22 | Lift/Generator /Substation /Solar work | N/A |
23 | Boundary wall /Ground floor development work | N/A |
24 | Roof top finishing work | N/A |
25 | Roof top Gardening work | N/A |
26 | Gardening work | N/A |
27 | Fair face finishing | N/A |
28 | Artificial fair face | N/A |
29 | Kitchen ver. Railing | N/A |
30 | Outside AC lover | N/A |
31 | Fir work | N/A |
32 | Swimming pool works | N/A |
32 | Pavement tiles | N/A |
33 | Pvc false ceiling works | N/A |
16604