Amabilia

Mohakhali, Dhaka

Completion Date

April 2026

Status Updated

April, 2024

SL. No Name of the work Progress details
01 Shore pile 100% completed
Tie beam 100% completed
02 Earth cutting 100% Completed
03 Foundation Casting 100% Completed
03A Sub-Structure Work 60% Completed (Basement Column, R/W casting completed)
04 Supper structure
05 Electrical conducting work  

 

06 Door frame fitting work
07 Sanitary & plumbing line work (Ace drain water line, ver- vertical line)
08 In side Plastering work
09 Electrical cable wiring work
10 Wall tiles work
11 Common sanitary & Plumbing line work
12 Outside plastering work
13 Floor tiles/Marble work
14 L.C.C work
15 Grill & Railing work
16 Inside paint & Polishing work
17 Switch -Socket fitting work
18 Outside paint work
19 Door shutter work
20 Aluminum/Glazing work
21 Tiles Pointing work & Marble finishing work
22 Commode – Basin fitting work and C.P fittings work  

 

23 Lift/Generator /Substation /Solar work
24 Boundary wall /Ground floor development work
25 Roof top finishing work
26 Roof top Gardening work