Amabilia

Mohakhali, Dhaka

Expected Completion Date

April 2026

Status Updated

September, 2025

SL. No Name of the work Progress details
01 Foundation work 100 %
02 Super Structure work 98%
03 Block work 97 %
03 Panel Work 50 %
05 Electrical conduiting work 40 %
06 Door frame fitting work 40 %
07 Sanitary & plumbing line work 35 %
08 In side Plastering work 60 %
09 Electrical cable wiring work Not Yet Started.
10 Wall tiles& floor tiles work Not Yet Started.
11 Common sanitary & Plumbing line work Not Yet Started.
12 Outside plastering work 30 %
13 Floor tiles/Marble work Not Yet Started.
14 L.C.C work Not Yet Started.
15 Grill & Railing work Not Yet Started.
16 Inside paint & Polishing work Not Yet Started.
17 Switch -Socket fitting work Not Yet Started.
18 Outside paint work Not Yet Started.
19 Door shutter work Not Yet Started.
20 Aluminum/Glazing work Not Yet Started.
21 Tiles Pointing work & Marble finishing work Not Yet Started.
22 Commode – Basin fitting work and C.P fittings work Not Yet Started.
23 Lift/Generator /Substation /Solar work Not Yet Started.
24 Boundary wall /Ground floor development work 30 %
25 Roof top finishing work 20 %
26 Roof top Gardening work Not Yet Started.
27 Gardening work Not Yet Started.
28 Fair face finishing Not Yet Started.
29 Artificial fair face Not Yet Started.
30 Kitchen ver. Railing Not Yet Started.
31 Outside AC lover Not Yet Started.
32 Fir work Not Yet Started.
33 Swimming pool works Not Yet Started.
34 Pavement tiles Not Yet Started.
35 Pvc false ceiling works Not Yet Started.