West Gate

Dhanmondi, Dhaka

Expected Completion Date

April 2026

Status Updated

May, 2025

SL. No Name of the work Progress details
01 Service pile 100%.
02 Grade beam 100%
03 Earth cutting 100%
04 Pile cap casting 100%
05 Supper structure 1.Ground Floor Column and Slab Casting 100% Complete.

2.1st Floor to 9th floor slab and column 100%.

3.Roof top parapet wall 70%

4.Roof top design wall 60%

5.Overhead water tank 100%

6.lift machine room 70%

 

 

06

 

 

 

Panel work & Block Work 3rd floor panel work 80%, 4rth floor panel work 80%, 5th floor panel work 60%, 6th floor panel work 20%,

Block work 3rd floor 80%,4rth floor 80%,5th floor 80%,6th floor 80%,7th floor 80%,8th floor 80%,9th floor 80%.

07 Electrical conducting work 3rd & 4rth floor vertical wearing 60%, 5th 40%, 6th floor 30%,7th floor 30%,8th floor 30%,9th floor 30%.
08 Door frame fitting work Not Yet Started.
09 Sanitary & plumbing line work (Ace drain water line, vertical line) Not Yet Started.
10 In side Plastering work GF ceiling plaster 30%, 2nd floor 80%,3rd floor 80%,4rth floor80%,5th floor80%,6th floor80%, 7th floor 80%, 8th floor 80%, 9th floor 80%.

 

 

 

10 Electrical cable wiring work Not Yet Started.
11 Wall tiles work Not Yet Started.
12 Common sanitary & Plumbing line work Not Yet Started.
13 Outside plastering work Not Yet Started.
14 Floor tiles Not Yet Started.
14 L.C.C work Not Yet Started.
15 Grill & Railing work Not Yet Started.
16 Inside paint & Polishing work Not Yet Started.
17 Switch -Socket fitting work Not Yet Started.
18 Outside paint work Not Yet Started.
19 Door shutter work Not Yet Started.
20 Aluminum/Glazing work Not Yet Started.
21 Tiles Pointing work & Marble finishing work Not Yet Started.
22 Commode – Basin fitting work and C.P fittings work Not Yet Started.
23 Lift/Generator /Substation /Solar work Not Yet Started.
24 Boundary wall /Ground floor development work Not Yet Started.
25 Roof top finishing work Not Yet Started.
26 Roof top Gardening work Not Yet Started.