Domus

Block K, Bashundhara R/A

Expected Completion Date

May 2026

Status Updated

April, 2026

SL. No Name of the work Progress details
01 Foundation work 100% Completed
02 Super Structure work 100% Completed
03 Block work  100%  Completed
04 Electrical  conduit  work 100% completed
05 Door frame fitting work 100% complete
06 Sanitary & plumbing line  work 100% complete
07 In side Plastering work 100% complete
08 Electrical cable wiring work 98% complete
09 Wall tiles  work 97% complete
10 Common sanitary & Plumbing line work 93% complete
11 Outside plastering work 100% complete
12 Floor tiles/Marble work 94% complete
13 L.C.C work 100% complete
14 Grill & Railing work 97% complete
15 Inside paint & Polishing work 45%
16 Switch -Socket fitting work N/A
17 Outside paint work 20%
18 Door shutter work N/A
19 Aluminum/Glazing work 85% complete
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work 5% complete
22 Lift/Generator /Substation /Solar work 85% complete
23 Boundary wall /Ground floor development work 89% complete
24 Roof top finishing work 75% complete
25 Roof top Gardening work N/A

 