Expected Completion Date
December 2027
Status Updated
December, 2025
| SL. No | Name of the work | Location | Progress details | Remarks |
| 01 | Foundation
work |
Tower-1
Tower-2 |
100%completed
100%completed |
|
| 02 | Basement work | Tower-1
Tower-2 |
100%completed
100%completed
|
|
| 03 | Super Structure Work | Tower-1 , 4th Floor
|
Column Casting ongoing | |
| 04 | Super Structure Work | Tower-2, 7th Floor
|
Slab shuttering work ongoing | |
| 05 | Block Work | Apartment =T2A2
Apartment =T2B2 Apartment =T2C2 Apartment =T2D2 Apartment =T2A2 Apartment =T2B2 Apartment =T2C2 Apartment =T2D2 Apartment =T2A3 Apartment =T2B3 Apartment =T2C3 Apartment =T2D3 Apartment =T2A4 Apartment =T2B4 Apartment =T2C4 Apartment =T2D4 |
20%
20% 30% 30% 30% 20% 20% 30% 30% 20% 20% 30% 30% 20% 20% 30% |
|
| 04 | Electrical conduiting work | |||
| 05 | Door frame fitting work | |||
| 06 | Sanitary & plumbing line work |
|
||
| 07 | In side Plastering work |
|
||
| 08 | Electrical cable wiring work | |||
| 09 | Wall tiles work | |||
| 10 | Common sanitary & Plumbing line work | |||
| 11 | Outside plastering work | |||
| 12 | Floor tiles/Marble work |
|
||
| 13 | L.C.C work | |||
| 14 | Grill & Railing work | |||
| 15 | Inside paint & Polishing work | |||
| 16 | Switch -Socket fitting work | |||
| 17 | Outside paint work | |||
| 18 | Door shutter work | |||
| 19 | Aluminum work | |||
| 20 | Tiles Pointing work & Marble finishing work | |||
| 21 | Commode – Basin fitting work and C.P fittings work | |||
| 22 | Lift/Generator /Substation /Solar work | |||
| 23 | Boundary wall /Ground floor development work | |||
| 24 | Roof top finishing work | |||
| 25 | Roof top Gardening work G.F Garden work |