La Montana

Moghbazar, Dhaka

Expected Completion Date

December 2027

Status Updated

December, 2025

SL. No Name of the work Location Progress details Remarks
01 Foundation

work

Tower-1

Tower-2

100%completed

100%completed

 
02 Basement work Tower-1

Tower-2

100%completed

100%completed

 

 
03 Super Structure Work  Tower-1 , 4th  Floor

 

Column Casting ongoing  
04 Super Structure Work Tower-2, 7th Floor

 

Slab shuttering work ongoing  
05 Block Work Apartment =T2A2

Apartment =T2B2

Apartment =T2C2

Apartment =T2D2

Apartment =T2A2

Apartment =T2B2

Apartment =T2C2

Apartment =T2D2

Apartment =T2A3

Apartment =T2B3

Apartment =T2C3

Apartment =T2D3

Apartment =T2A4

Apartment =T2B4

Apartment =T2C4

Apartment =T2D4

20%

20%

30%

30%

30%

20%

20%

30%

30%

20%

20%

30%

30%

20%

20%

30%

 
04 Electrical conduiting work      
05 Door frame fitting work      
06 Sanitary & plumbing line work  

 

   
07 In side Plastering work  

 

   
08 Electrical cable wiring work      
09 Wall tiles work      
10 Common sanitary & Plumbing line work      
11 Outside plastering work      
12 Floor tiles/Marble work  

 

   
13 L.C.C work      
14 Grill & Railing work      
15 Inside paint & Polishing work      
16 Switch -Socket fitting work      
17 Outside paint work      
18 Door shutter work      
19 Aluminum work      
20 Tiles Pointing work & Marble finishing work      
21 Commode – Basin fitting work and C.P fittings work      
22 Lift/Generator /Substation /Solar work      
23 Boundary wall /Ground floor development work      
24 Roof top finishing work      
25 Roof top Gardening work G.F Garden work      

 

16604