Adora

Block J, Bashundhara R/A

Expected Completion Date

April 2026

Status Updated

September, 2025

SL. No Name of the work Progress details
01 Foundation work Foundation Completed,
02 Super Structure work 100%
03 Block Work A2 = 100%, B2= 100%, A3 = 100%, B3= 100% ,A4= 100%, B4= 100% ,A5 = 100%, B5= 100% A6= 100%, B6= 100%, A7= 100%, B7= 100%, A8= 100%, B8= 100%, A9= 90%, B9= 90%,
04 Electrical conducting work 85%
05 Door frame fitting work A2 = 100%, B2= 100%, A3 = 100%, B3= 100% A4= 100%, B4= 100%, A5= 100%, B5= 100%, A6= 100%, B6= 100% ,A7= 100%, B7= 100%, A8= 100%, B8= 100%
06 Sanitary & plumbing line work A2 = 30%, B2= 30%, A3 = 30%, B3= 30% ,B4= 30%, A4 = 30%, A5 = 30% ,B5= 30%
07 In side Plastering work A2 = 100%, B2= 100%, A3 = 100%, B3= 100% ,A4= 100%, B4= 100% ,A5= 100%, B5= 90%, A6= 90%, B6= 90%, A7= 95%, B7= 95%, A8= 55%, B8= 55%,
08 Electrical cable wiring work 20%
09 Wall tiles work 25%
10 Common sanitary & Plumbing line work N/A
11 Outside plastering work 5%
12 Floor tiles/Marble work N/A
13 L.C.C work N/A
14 Grill & Railing work N/A
15 Inside paint & Polishing work N/A
16 Switch -Socket fitting work N/A
17 Outside paint work N/A
18 Door shutter work N/A
19 Aluminum work N/A
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work N/A
24 Roof top finishing work

 

20%
25 Roof top Gardening work G.F Garden work N/A

16604