bti Celebration Point

Plot: 3 & 5, Road: 113/A, Gulshan-2, Dhaka-1212

Adora

Bashundhara R/A, Dhaka
Expected Completion Date July 2026
Status Updated May, 2026
Back to all projects
Adora

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Foundation work Foundation Completed,
02 Super Structure work 100%
03 Block Work A2 = 100%, B2= 100%, A3 = 100%, B3= 100% ,A4= 100%, B4= 100%, A5 = 100%, B5= 100% A6= 100%, B6= 100%, A7= 100%, B7= 100%, A8= 100%, B8= 100%, A9=100%, B9= 100%,
04 Electrical conducting work 85%
05 Door frame fitting work A2 = 100%, B2= 100%, A3 = 100%, B3= 100% A4= 100%, B4= 100%, A5= 100%, B5= 100%, A6= 100%, B6= 100% ,A7= 100%, B7= 100%, A8= 100%, B8= 100%
06 Sanitary & plumbing line work A2 = 90%, B2= 90%, A3 =90%, B3=9% ,B4= 90%, A4 = 90%, A5 = 90% ,B5= 90% A6 = 90% ,B6= 90% ,A7 = 90% ,B7= 90%
07 In side Plastering work A2 = 100%, B2= 100%, A3 = 100%, B3= 100% ,A4= 100%, B4= 100% ,A5= 100%, B5= 90%, A6= 100%, B6= 100%, A7= 100%, B7= 100%, A8= 100%, B8= 100%,
08 Electrical cable wiring work 100%
09 Wall tiles work 95%
10 Common sanitary & Plumbing line work N/A
11 Outside plastering work 100%
12 Floor tiles/Marble work 100%
13 L.C.C work 100%
14 Grill & Railing work 100%
15 Inside paint & Polishing work 70%
16 Switch -Socket fitting work 80%
17 Outside paint work 50%
18 Door shutter work 100%
19 Aluminum work 80%
20 Tiles Pointing work & Marble finishing work 40%
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work N/A
24 Roof top finishing work

 

85%
25 Roof top Gardening work G.F Garden work 50%