Expected Completion Date
November 2025
Status Updated
September, 2025
| SL. No | Name of the work | Progress details |
| 01 | Foundation work | Foundation 100% Completed |
| 02 | Super Structure work | 100% |
| 03 | Block Work | A-1 =100%, A-2= 100%, A-3 = 100%, A-4 =100%, A-5 =100%, A-6 =100%, A8= 100% |
| 04 | Electrical conducting work | A-1 =100%, A-2= 100%, A-3 = 100%, A-4 =100%, A-5 =100%, A-6 =100%, A8= 100% |
| 05 | Door frame fitting work | A-1 =100%, A-2= 100%, A-3 = 100%, A-4 =100%, A-5 =100%, A-6 =100%, A8= 100% |
| 06 | Sanitary & plumbing line work | 80% |
| 07 | In side Plastering work | A-1 =100%, A-2= 100%, A-3 = 100%, A-4 =100%, A-5 =100%, A-6 =100%, A8= 100% |
| 08 | Electrical cable wiring work | 90% |
| 09 | Wall tiles work | A-1 =100%, B-1= 100%, A-2 =100%, A-3 = 100%, A-4 =100%, A-5 =100%, A-6 =100%, A7= 100% |
| 10 | Common sanitary & Plumbing line work | 80% |
| 11 | Outside plastering work | 98% |
| 12 | Floor tiles/Marble work | A-1 =100%, B-1= 100%, A-2 =100%, A-3 = 100%, A-4 =100%, A-5 =100%, A-6 =100%, A7= 100% |
| 13 | L.C.C work | 100% |
| 14 | Grill & Railing work | 100% |
| 15 | Inside paint & Polishing work | 50% |
| 16 | Switch -Socket fitting work | 30% |
| 17 | Outside paint work | 30% |
| 18 | Door shutter work | 100% |
| 19 | Aluminum work | 90% |
| 20 | Tiles Pointing work & Marble finishing work | N/A |
| 21 | Commode – Basin fitting work and C.P fittings work | N/A |
| 22 | Lift/Generator /Substation /Solar work | 50% |
| 23 | Boundary wall /Ground floor development work | 60% |
| 24 | Roof top finishing work | 80% |
| 25 | Roof top Gardening work G.F Garden work | N/A |