Altus

Block L, Bashundhara R/A

Expected Completion Date

September 2025

Status Updated

May, 2025

SL. No Name of the work Progress details
01 Foundation work Foundation 100% Completed
02 Super Structure work 100%
03 Block Work A-1 =100%, A-2= 100%, A-3 = 100%, A-4 =100%, A-5 =100%, A-6 =100%, A8= 100%
04 Electrical conducting work A-1 =100%, A-2= 100%, A-3 = 100%, A-4 =100%, A-5 =100%, A-6 =100%, A8= 100%
05 Door frame fitting work A-1 =100%, A-2= 100%, A-3 = 100%, A-4 =100%, A-5 =100%, A-6 =100%, A8= 100%
06 Sanitary & plumbing line work N/A
07 In side Plastering work A-1 =100%, A-2= 100%, A-3 = 100%, A-4 =100%, A-5 =100%, A-6 =100%, A8= 100%
08 Electrical cable wiring work 60%
09 Wall tiles work A-1 =10%, B-1= 10%, A-2 =40%, A-3 = 70%, A-4 =00%, A-5 =80%, A-6 =80%, A7= 80%
10 Common sanitary & Plumbing line work 60%
11 Outside plastering work 80%
12 Floor tiles/Marble work A-1 =0%, B-1= 0%, A-2 =40%, A-3 = 70%, A-4 =00%, A-5 =80%, A-6 =80%, A7= 80%
13 L.C.C work 100%
14 Grill & Railing work N/A
15 Inside paint & Polishing work N/A
16 Switch -Socket fitting work N/A
17 Outside paint work N/A
18 Door shutter work N/A
19 Aluminum work N/A
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work N/A
24 Roof top finishing work 40%
25 Roof top Gardening work G.F Garden work N/A

 