bti Celebration Point

Plot: 3 & 5, Road: 113/A, Gulshan-2, Dhaka-1212

Altus

Bashundhara R/A, Dhaka
Expected Completion Date February 2026
Status Updated December, 2025
Back to all projects
Altus

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Foundation work Foundation 100% Completed
02 Super Structure work 100%
03 Block Work A-1 =100%, A-2= 100%, A-3 = 100%, A-4 =100%, A-5 =100%, A-6 =100%, A8= 100%
04 Electrical conducting work A-1 =100%, A-2= 100%, A-3 = 100%, A-4 =100%, A-5 =100%, A-6 =100%, A8= 100%
05 Door frame fitting work A-1 =100%, A-2= 100%, A-3 = 100%, A-4 =100%, A-5 =100%, A-6 =100%, A8= 100%
06 Sanitary & plumbing line work 80%
07 In side Plastering work A-1 =100%, A-2= 100%, A-3 = 100%, A-4 =100%, A-5 =100%, A-6 =100%, A8= 100%
08 Electrical cable wiring work 90%
09 Wall tiles work A-1 =100%, B-1= 100%, A-2 =100%, A-3 = 100%, A-4 =100%, A-5 =100%, A-6 =100%, A7= 100%
10 Common sanitary & Plumbing line work 80%
11 Outside plastering work 98%
12 Floor tiles/Marble work A-1 =100%, B-1= 100%, A-2 =100%, A-3 = 100%, A-4 =100%, A-5 =100%, A-6 =100%, A7= 100%
13 L.C.C work 100%
14 Grill & Railing work 100%
15 Inside paint & Polishing work 100%
16 Switch -Socket fitting work 100%
17 Outside paint work 100%
18 Door shutter work 100%
19 Aluminum work 100%
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work 100%
23 Boundary wall /Ground floor development work 100%
24 Roof top finishing work 100%
25 Roof top Gardening work G.F Garden work 100%

 