Expected Completion Date
April 2026
Status Updated
September, 2025
SL. No | Name of the work | Progress details |
01 | Foundation work | 100 % |
02 | Super Structure work | 98% |
03 | Block work | 97 % |
03 | Panel Work | 50 % |
05 | Electrical conduiting work | 40 % |
06 | Door frame fitting work | 40 % |
07 | Sanitary & plumbing line work | 35 % |
08 | In side Plastering work | 60 % |
09 | Electrical cable wiring work | Not Yet Started. |
10 | Wall tiles& floor tiles work | Not Yet Started. |
11 | Common sanitary & Plumbing line work | Not Yet Started. |
12 | Outside plastering work | 30 % |
13 | Floor tiles/Marble work | Not Yet Started. |
14 | L.C.C work | Not Yet Started. |
15 | Grill & Railing work | Not Yet Started. |
16 | Inside paint & Polishing work | Not Yet Started. |
17 | Switch -Socket fitting work | Not Yet Started. |
18 | Outside paint work | Not Yet Started. |
19 | Door shutter work | Not Yet Started. |
20 | Aluminum/Glazing work | Not Yet Started. |
21 | Tiles Pointing work & Marble finishing work | Not Yet Started. |
22 | Commode – Basin fitting work and C.P fittings work | Not Yet Started. |
23 | Lift/Generator /Substation /Solar work | Not Yet Started. |
24 | Boundary wall /Ground floor development work | 30 % |
25 | Roof top finishing work | 20 % |
26 | Roof top Gardening work | Not Yet Started. |
27 | Gardening work | Not Yet Started. |
28 | Fair face finishing | Not Yet Started. |
29 | Artificial fair face | Not Yet Started. |
30 | Kitchen ver. Railing | Not Yet Started. |
31 | Outside AC lover | Not Yet Started. |
32 | Fir work | Not Yet Started. |
33 | Swimming pool works | Not Yet Started. |
34 | Pavement tiles | Not Yet Started. |
35 | Pvc false ceiling works | Not Yet Started. |