Amabilia

Mohakhali, Dhaka

Expected Completion Date

April 2026

Status Updated

October, 2024

SL. No Name of the work Progress details
01 Foundation work 100%, Basement roof slab casting completed.
02 Super Structure work 25 % Completed. 1st floor roof slab casting completed.
03 Block Work N/A
04 Electrical conducting work N/A
05 Door frame fitting work N/A
06 Sanitary & plumbing line work N/A
07 In side Plastering work N/A
08 Electrical cable wiring work N/A
09 Wall tiles& floor tiles work N/A

 

10 Common sanitary & Plumbing line work N/A
11 Outside plastering work N/A
12 Floor tiles/Marble work N/A
13 L.C.C work N/A
14 Grill & Railing work N/A
15 Inside paint & Polishing work N/A
16 Switch -Socket fitting work  N/A
17 Outside paint work N/A
18 Door shutter work N/A
19 Aluminum/Glazing work N/A
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work N/A
24 Roof top finishing work N/A
25 Roof top Gardening work N/A
26 Gardening work N/A
27 Fair face finishing N/A
28 Artificial fair face N/A
29 Kitchen ver. Railing N/A
30 Outside AC lover N/A
31 Fir work N/A
32 Swimming pool works N/A
32 Pavement tiles N/A
33 Pvc false ceiling works N/A

 

16604