Amabilia

Mohakhali, Dhaka

Expected Completion Date

April 2026

Status Updated

December, 2025

SL. No Name of the work Progress details
01 Foundation work 100 %
02 Super Structure work 98%
03 Block work 95 %
03 Panel Work 98 %
05 Electrical conducting work 85 %
06 Door frame fitting work 85 %
07 Sanitary & plumbing line work 70 %
08 In side Plastering work 80 %
09 Electrical cable wiring work 5 %
10 Wall tiles& floor tiles work 20

 

11 Common sanitary & Plumbing line work 70 %
12 Outside plastering work 70 %
13 Floor tiles/Marble work Not Yet Started
14 L.C.C work Not Yet Started
15 Grill & Railing work Not Yet Started
16 Inside paint & Polishing work Not Yet Started
17 Switch -Socket fitting work Not Yet Started
18 Outside paint work Not Yet Started
19 Door shutter work Not Yet Started
20 Aluminum/Glazing work Not Yet Started
21 Tiles Pointing work & Marble finishing work Not Yet Started
22 Commode – Basin fitting work and C.P fittings work Not Yet Started
23 Lift/Generator /Substation /Solar work Not Yet Started
24 Boundary wall /Ground floor development work 30 %
25 Roof top finishing work 50 %
26 Roof top Gardening work Not Yet Started
27 Gardening work Not Yet Started
28 Fair face finishing Not Yet Started
29 Artificial fair face Not Yet Started
30 Kitchen ver. Railing Not Yet Started
31 Outside AC lover Not Yet Started
32 Fir work Not Yet Started
33 Swimming pool works Not Yet Started
34 Pavement tiles Not Yet Started
35 Pvc false ceiling works Not Yet Started

 