Expected Completion Date
June 2025
Status Updated
March, 2025
SL. No | Name of the work | Progress details |
01 | I-Jost drive | Complete, |
02 | Earth cutting | Complete, |
03 | Mat casting | Complete, |
04 | Supper structure | 1)Basement Retaining wall,Column+Share wall casting,Basement Roof Slab Casting Complete,
2)Ground Floor Column+Share wall Casting Complete, 3)Ground Floor Roof slab(1st floor slab-Mezzanine part) Casting Complete, 4) )1st Floor Column+Share wall Casting Complete 5)2nd Floor slab Casting work complete. 6)2nd Floor Colunm casting Complete. 7)3rd Floor Slab Casting Work Complete, 8)3rd Floor Column Casting Work Complete, 9) 4th Floor Slab Casting Work Complete, 10) 4th Floor Column Casting Work Complete, 11)5th Floor Slab Casting Work Complete, 12)5th Floor Column Casting work Complete, 13)6th Floor Slab Casting Work Complete, 14)6th Floor Column Casting Complete, 15)7th Floor Slab Casting Complete. 16)7th Floor Column Casting Complete, 17) 8th Floor Slab Casting Complete, 18) 8th Floor Column Casting Complete, 19) ) 9th Floor Slab Casting Complete, 20) 10th Floor Slab Casting Complete, 21) 10th Floor Column Casting Complete, 22)11th Floor Slab Casting Work complete, 23) 11th Floor Column Casting 100% Complete, 24)11th Floor Roof Slab Casting Work Complete. 25) Above Roof Top Floor Column Casting 80% Complete, 26)OHWT -1,Bottom Slab+ Wall Casting Complete, 27)Above Roof Swimming Pool Bottom Slab Shutter Work Complete, 28)Above Roof Swimming Pool Wall Casting 100%Complete, 29)Above Roof Swimming Pool,Deck Floor Slab Casting 100%Complete, 30)Above Roof Swimming Pool, Deck Slab,OHWT Top Slab Casting 100%Complete,
|
05 | Electrical conducting work | 1)Basement Roof slab PVC Pipe Conduit Work Complete,
2) Ground Floor Roof slab/1st Floor Slab(Mezzanine part) PVC Pipe Conduit work Complete, 3) 2nd Floor slab PVC Pipe Conduit work Complete. 4)3rd Floor slab PVC Pipe Conduit work Complete, 5) 4th Floor slab PVC Pipe Conduit work Complete, 6) 5th Floor slab PVC Pipe Conduit work Complete, 7) 6th Floor slab PVC Pipe Conduit work Complete, 8) 7th Floor slab PVC Pipe Conduit work Complete, 9) 8th Floor slab PVC Pipe Conduit work Complete, 10) 9th Floor slab PVC Pipe Conduit work Complete. 11) 10th Floor slab PVC Pipe Conduit work Complete. 12) 11th Floor slab PVC Pipe Conduit work Complete, 13) 12th Floor slab(Roof of 11th Floor) PVC Pipe Conduit work Complete,
14)3rd to 8th Floor Internal W/G Pipe+ MK Box Work 80% Complete, 15)2nd+9th Floor Internal W/G Pipe+ MK Box Work 80% Complete, 16)10th Floor Internal W/G Pipe+ MK Box Work 80% Complete, 17)11th Floor Internal W/G Pipe+ MK Box Work 80% Complete,
|
06 | Door frame fitting work | 1)2nd to 8th Floor Door frame fitting work 80%Complete.
2)9th to 10th Floor Door frame fitting work 80%Complete.
|
07 | Sanitary & plumbing line work(Ace drain water line, ver – vertical line) | 1) 2nd Floor slab Verandah Upvc Pipe Conduit work Complete.
2)3rd Floor slab Verandah Upvc Pipe Conduit work Complete, 3) 4th Floor slab Verandah Upvc Pipe Conduit work Complete, 4) 5th Floor slab Verandah Upvc Pipe Conduit work Complete, 5) 6th Floor slab Verandah Upvc Pipe Conduit work Complete. 6) 7th Floor slab Verandah Upvc Pipe Conduit work Complete, 7) 8th Floor slab Verandah Upvc Pipe Conduit work Complete, 8) 9th Floor slab Verandah Upvc Pipe Conduit work Complete 9) 10th Floor slab Verandah Upvc Pipe Conduit work Complete, 10) 11th Floor slab Verandah Upvc Pipe Conduit work Complete, 11)All Floor Sanitary Duct Vertical Upvc Line 90% Complete, 12)5th Floor PPR Pipe Wairing 80%Complete, 13)7th Floor PPR Pipe Wairing 70%Complete, 14)9th Floor PPR Pipe Wairing 80%Complete, |
08 | In side Plastering work | 1)Basement Ceiling Plaster Work 80% complete,
2)1st Floor Ceiling Plaster Work 70% Complete 3)2nd Floor Ceiling Plaster Work 90% Complete, 4) 3rd Floor Ceiling Plaster Work 90% Complete, 5)4th Floor Ceiling Plaster Work 90% Complete 6) 5th Floor Ceiling Plaster Work 90% Complete. 7)6th Floor Ceiling Plaster Work 90% Complete. 8)7th Floor Ceiling Plaster Work 90% Complete. 9) 8th Floor Ceiling Plaster Work 90% Complete, 10) 9th Floor Ceiling Plaster Work 90% Complete, 11) 10th Floor Ceiling Plaster Work 90% Complete, 12)Basement Wall Plaster Work 70% complete, 13) 2nd Floor Internal Plaster Work 90% Complete 14)3rd Floor Internal Plaster Work 80% Complete 15)4th Floor Internal Plaster Work 90% Complete, 16)5th,6th,7th,9th Floor Internal Plaster Work 90% Complete, 17) 10th Floor Internal Plaster Work 90% Complete, 18)11th Floor Internal Plaster Work 80% Complete,
|
09 | Electrical cable wiring work | Basement Ceiling Cable Wiring Work 90% complete.
|
10 | Inside Panel slab Fitting work | 1)2nd Floor Panel wall Fitting Work 90% Complete,
2) 3rd Floor Panel wall Fitting Work 100% Complete, 3) 4th Floor Panel wall Fitting Work 100% Complete, 4)5th Floor Panel wall Fitting Work 100% Complete. 5)6th Floor Panel wall Fitting Work 100% Complete. 6)7th Floor Panel wall Fitting Work 100% Complete 7)8th Floor Panel wall Fitting Work 100% Complete 8) 9th Floor Panel wall Fitting Work 100% Complete, 9) 10th Floor Panel wall Fitting Work 100% Complete, 10) 11th Floor Panel wall Fitting Work 90% Complete,
|
11 | Common sanitary & Plumbing line work | |
12 | Outside plastering work | 1)North Out Side Plaster Work 80% Complete,
2)East Out Side Plaster Work 70% Complete, 3)West Out Side Plaster Work 20% Complete,
|
13 | Wall/Floor tiles/Marble work | 1)5th Floor Wall Tiles 70% Complete, |
14 | L.C.C work | |
15 | Grill & Railing work | |
16 | Inside paint & Polishing work | |
17 | Switch -Socket fitting work | |
18 | Outside paint work | |
19 | Door shutter work | |
20 | Aluminum/Glazing work | |
21 | Tiles Pointing work & Marble finishing work | |
22 | Commode – Basin fitting work and C.P fittings work |
|
23 | Lift/Generator /Substation /Solar work | |
24 | Boundary wall /Ground floor development work | 1)G/Floor Boundary Wall Work 30% Complete, |
25 | Roof top finishing work | |
26 | Roof top Gardening work |
16604