Aqualuna

Dhanmondi, Dhaka

Completion Date

June 2025

Status Updated

March, 2024

SL. No Name of the work Progress details
01 I-Jost drive Complete,
02 Earth cutting Complete,
03 Mat casting Complete,
04 Supper structure 1)Basement Retaining wall,Column+Share wall casting,Basement Roof Slab Casting Complete,

2)Ground Floor Column+Share wall Casting Complete,

3)Ground Floor Roof slab(1st floor slab-Mezzanine part) Casting Complete,

4) )1st Floor Column+Share wall Casting Complete

5)2nd Floor slab Casting work complete.

6)2nd Floor Colunm casting Complete.

7)3rd Floor Slab Casting Work Complete,

8)3rd Floor Column Casting Work Complete,

9) 4th Floor Slab Casting Work Complete,

10) 4th Floor Column Casting Work Complete,

11)5th Floor Slab Casting Work Complete,

12)5th Floor Column Casting  work Complete,

13)6th Floor Slab Casting Work Complete,

14)6th Floor Column Casting Complete,

15)7th Floor Slab Casting Complete.

16)7th Floor Column Casting Complete,

17) 8th Floor Slab Casting Complete,

18) 8th Floor Column Casting Complete,

05 Electrical  conducting work 1)Basement Roof slab PVC Pipe Conduit Work Complete,

2) Ground Floor Roof slab/1st Floor Slab(Mezzanine part) PVC Pipe Conduit work Complete,

3) 2nd Floor slab PVC Pipe Conduit work Complete.

4)3rd Floor slab PVC Pipe Conduit work Complete,

5) 4th Floor slab PVC Pipe Conduit work Complete,

6) 5th Floor slab PVC Pipe Conduit work Complete,

7) 6th Floor slab PVC Pipe Conduit work Complete,

8) 7th Floor slab PVC Pipe Conduit work Complete,

9) 8th Floor slab PVC Pipe Conduit work Complete

06 Door frame fitting work  
07 Sanitary & plumbing line  work(Ace drain water line, ver – vertical line) 1) 2nd Floor slab Verandah Upvc Pipe Conduit work Complete.

2)3rd Floor slab Verandah Upvc Pipe Conduit work Complete,

3) 4th Floor slab Verandah Upvc Pipe Conduit work Complete,

4) 5th Floor slab Verandah Upvc Pipe Conduit work Complete,

5) 6th Floor slab Verandah Upvc Pipe Conduit work Complete.

6) 7th Floor slab Verandah Upvc Pipe Conduit work Complete,

7) 8th Floor slab Verandah Upvc Pipe Conduit work Complete,

08 In side Plastering work 1)Basement Ceiling Plaster Work 80% complete,

2)1st Floor Ceiling Plaster Work 70% Complete

3)2nd Floor Ceiling Plaster Work 90% Complete,

4) 3rd Floor Ceiling Plaster Work 90% Complete,

5)4th Floor Ceiling Plaster Work 90% Complete

6) 5th Floor Ceiling Plaster Work 90% Complete.

09 Electrical cable wiring work Basement Ceiling Cable Wiring Work 90% complete.

 

 

10  Inside Panel slab Fitting  work 1)2nd Floor Panel Fitting Work 80% Complete,

2) 3rd Floor Panel Fitting Work 70% Complete,

3) 4th Floor Panel Fitting Work 70% Complete

11 Common sanitary & Plumbing line work  
12 Outside plastering work  
13 Floor tiles/Marble work  
14 L.C.C work  
15 Grill & Railing work  
16 Inside paint & Polishing work  
17 Switch -Socket fitting work  
18 Outside paint work  
19 Door shutter work  
20 Aluminum/Glazing work  
21 Tiles Pointing work & Marble finishing work  
22 Commode – Basin fitting work and C.P fittings work  

 

23 Lift/Generator /Substation /Solar work  
24 Boundary wall /Ground floor development work  
25 Roof top finishing work  
26 Roof top Gardening work  