Completion Date
June 2025
Status Updated
March, 2024
SL. No | Name of the work | Progress details |
01 | I-Jost drive | Complete, |
02 | Earth cutting | Complete, |
03 | Mat casting | Complete, |
04 | Supper structure | 1)Basement Retaining wall,Column+Share wall casting,Basement Roof Slab Casting Complete,
2)Ground Floor Column+Share wall Casting Complete, 3)Ground Floor Roof slab(1st floor slab-Mezzanine part) Casting Complete, 4) )1st Floor Column+Share wall Casting Complete 5)2nd Floor slab Casting work complete. 6)2nd Floor Colunm casting Complete. 7)3rd Floor Slab Casting Work Complete, 8)3rd Floor Column Casting Work Complete, 9) 4th Floor Slab Casting Work Complete, 10) 4th Floor Column Casting Work Complete, 11)5th Floor Slab Casting Work Complete, 12)5th Floor Column Casting work Complete, 13)6th Floor Slab Casting Work Complete, 14)6th Floor Column Casting Complete, 15)7th Floor Slab Casting Complete. 16)7th Floor Column Casting Complete, 17) 8th Floor Slab Casting Complete, 18) 8th Floor Column Casting Complete, |
05 | Electrical conducting work | 1)Basement Roof slab PVC Pipe Conduit Work Complete,
2) Ground Floor Roof slab/1st Floor Slab(Mezzanine part) PVC Pipe Conduit work Complete, 3) 2nd Floor slab PVC Pipe Conduit work Complete. 4)3rd Floor slab PVC Pipe Conduit work Complete, 5) 4th Floor slab PVC Pipe Conduit work Complete, 6) 5th Floor slab PVC Pipe Conduit work Complete, 7) 6th Floor slab PVC Pipe Conduit work Complete, 8) 7th Floor slab PVC Pipe Conduit work Complete, 9) 8th Floor slab PVC Pipe Conduit work Complete |
06 | Door frame fitting work | |
07 | Sanitary & plumbing line work(Ace drain water line, ver – vertical line) | 1) 2nd Floor slab Verandah Upvc Pipe Conduit work Complete.
2)3rd Floor slab Verandah Upvc Pipe Conduit work Complete, 3) 4th Floor slab Verandah Upvc Pipe Conduit work Complete, 4) 5th Floor slab Verandah Upvc Pipe Conduit work Complete, 5) 6th Floor slab Verandah Upvc Pipe Conduit work Complete. 6) 7th Floor slab Verandah Upvc Pipe Conduit work Complete, 7) 8th Floor slab Verandah Upvc Pipe Conduit work Complete, |
08 | In side Plastering work | 1)Basement Ceiling Plaster Work 80% complete,
2)1st Floor Ceiling Plaster Work 70% Complete 3)2nd Floor Ceiling Plaster Work 90% Complete, 4) 3rd Floor Ceiling Plaster Work 90% Complete, 5)4th Floor Ceiling Plaster Work 90% Complete 6) 5th Floor Ceiling Plaster Work 90% Complete. |
09 | Electrical cable wiring work | Basement Ceiling Cable Wiring Work 90% complete.
|
10 | Inside Panel slab Fitting work | 1)2nd Floor Panel Fitting Work 80% Complete,
2) 3rd Floor Panel Fitting Work 70% Complete, 3) 4th Floor Panel Fitting Work 70% Complete |
11 | Common sanitary & Plumbing line work | |
12 | Outside plastering work | |
13 | Floor tiles/Marble work | |
14 | L.C.C work | |
15 | Grill & Railing work | |
16 | Inside paint & Polishing work | |
17 | Switch -Socket fitting work | |
18 | Outside paint work | |
19 | Door shutter work | |
20 | Aluminum/Glazing work | |
21 | Tiles Pointing work & Marble finishing work | |
22 | Commode – Basin fitting work and C.P fittings work |
|
23 | Lift/Generator /Substation /Solar work | |
24 | Boundary wall /Ground floor development work | |
25 | Roof top finishing work | |
26 | Roof top Gardening work |