Expected Completion Date
To be Announced
Status Updated
March, 2025
SL. No | Name of the work | Progress details |
01 | Foundation work | 100% Completed. |
02 | Super Structure work | 20 % Completed. (2nd floor roof work going on) |
03 | Block Work | Not yet started. |
04 | Electrical conduiting work | Not yet started. |
05 | Door frame fitting work | Not yet started. |
06 | Sanitary & plumbing line work (AC drain water line, verandah- vertical line) | Not yet started. |
07 | In side Plastering work | Not yet started. |
08 | Electrical cable wiring work | Not yet started. |
09 | Wall tiles work | Not yet started. |
10 | Common sanitary & Plumbing line work | Not yet started. |
11 | Outside plastering work | Not yet started. |
12 | Floor tiles/Marble work | Not yet started. |
13 | L.C.C work | Not yet started. |
14 | Grill & Railing work | Not yet started. |
15 | Inside paint & Polishing work | Not yet started. |
16 | Switch -Socket fitting work | Not yet started. |
17 | Outside paint work | Not yet started. |
18 | Door shutter work | Not yet started. |
19 | Aluminum/Glazing work | Not yet started. |
20 | Tiles Pointing work & Marble finishing work | Not yet started. |
21 | Commode – Basin fitting work and C.P fittings work | Not yet started. |
22 | Lift/Generator /Substation /Solar work | Not yet started. |
23 | Boundary wall /Ground floor development work | Not yet started. |
24 | Roof top finishing work | Not yet started. |
25 | Roof top Gardening work | Not yet started. |