Beverly Residence

Gulshan, Dhaka

Expected Completion Date

March 2027

Status Updated

November, 2025

SL. No Name of the work Progress details
01 Foundation work 100 %
02 Super Structure work 80%
03 Block Work 15%
04 Electrical conducting work 20 %
05 Door frame fitting work Not Yet Started
06 Sanitary & plumbing line work Not Yet Started
07 In side Plastering work 10%
08 Electrical cable wiring work Not Yet Started
09 Wall tiles& floor tiles work Not Yet Started
10 Common sanitary & Plumbing line work Not Yet Started
11 Outside plastering work Not Yet Started
12 Floor tiles/Marble work Not Yet Started
13 L.C.C work Not Yet Started
14 Grill & Railing work Not Yet Started
15 Inside paint & Polishing work Not Yet Started
16 Switch -Socket fitting work Not Yet Started
17 Outside paint work Not Yet Started
18 Door shutter work Not Yet Started
19 Aluminum/Glazing work Not Yet Started
20 Tiles Pointing work & Marble finishing work Not Yet Started
21 Commode – Basin fitting work and C.P fittings work Not Yet Started
22 Lift/Generator /Substation /Solar work Not Yet Started
23 Boundary wall /Ground floor development work Not Yet Started
24 Roof top finishing work Not Yet Started
25 Roof top Gardening work Not Yet Started
26 Gardening work Not Yet Started
27 Fair face finishing Not Yet Started
28 Artificial fair face Not Yet Started
29 Kitchen ver. Railing Not Yet Started
30 Outside AC lover Not Yet Started
31 Fir work Not Yet Started
32 Swimming pool works Not Yet Started
32 Pavement tiles Not Yet Started
33 Pvc false ceiling works Not Yet Started