Expected Completion Date
March 2027
Status Updated
August, 2025
SL. No | Name of the work | Progress details |
01 | Foundation work | 100 % |
02 | Super Structure work | 50 % |
03 | Block Work | 5% |
04 | Electrical conducting work | 15 % |
05 | Door frame fitting work | Not Yet Started. |
06 | Sanitary & plumbing line work | Not Yet Started. |
07 | In side Plastering work | 5% |
08 | Electrical cable wiring work | Not Yet Started. |
09 | Wall tiles& floor tiles work | Not Yet Started. |
10 | Common sanitary & Plumbing line work | Not Yet Started. |
11 | Outside plastering work | Not Yet Started. |
12 | Floor tiles/Marble work | Not Yet Started. |
13 | L.C.C work | Not Yet Started. |
14 | Grill & Railing work | Not Yet Started. |
15 | Inside paint & Polishing work | Not Yet Started. |
16 | Switch -Socket fitting work | Not Yet Started. |
17 | Outside paint work | Not Yet Started. |
18 | Door shutter work | Not Yet Started. |
19 | Aluminum/Glazing work | Not Yet Started. |
20 | Tiles Pointing work & Marble finishing work | Not Yet Started. |
21 | Commode – Basin fitting work and C.P fittings work | Not Yet Started. |
22 | Lift/Generator /Substation /Solar work | Not Yet Started. |
23 | Boundary wall /Ground floor development work | Not Yet Started. |
24 | Roof top finishing work | Not Yet Started. |
25 | Roof top Gardening work | Not Yet Started. |
26 | Gardening work | Not Yet Started. |
27 | Fair face finishing | Not Yet Started. |
28 | Artificial fair face | Not Yet Started. |
29 | Kitchen ver. Railing | Not Yet Started. |
30 | Outside AC lover | Not Yet Started. |
31 | Fir work | Not Yet Started. |
32 | Swimming pool works | Not Yet Started. |
32 | Pavement tiles | Not Yet Started. |
33 | Pvc false ceiling works | Not Yet Started. |