Beverly Residence

Gulshan, Dhaka

Expected Completion Date

To be Announced

Status Updated

March, 2025

SL. No Name of the work Progress details
01 Foundation work 100% Completed.
02 Super Structure work 20 % Completed. (2nd floor roof work going on)
03 Block Work Not yet started.
04 Electrical conduiting work Not yet started.
05 Door frame fitting work Not yet started.
06 Sanitary & plumbing line work (AC drain water line, verandah- vertical line) Not yet started.
07 In side Plastering work Not yet started.
08 Electrical cable wiring work Not yet started.
09 Wall tiles work Not yet started.
10 Common sanitary & Plumbing line work Not yet started.
11 Outside plastering work Not yet started.
12 Floor tiles/Marble work Not yet started.
13 L.C.C work Not yet started.
14 Grill & Railing work Not yet started.
15 Inside paint & Polishing work Not yet started.
16 Switch -Socket fitting work Not yet started.
17 Outside paint work Not yet started.
18 Door shutter work Not yet started.
19 Aluminum/Glazing work Not yet started.
20 Tiles Pointing work & Marble finishing work Not yet started.
21 Commode – Basin fitting work and C.P fittings work Not yet started.
22 Lift/Generator /Substation /Solar work Not yet started.
23 Boundary wall /Ground floor development work Not yet started.
24 Roof top finishing work Not yet started.
25 Roof top Gardening work Not yet started.