bti Celebration Point

Plot: 3 & 5, Road: 113/A, Gulshan-2, Dhaka-1212

Birchwood

Bashundhara R/A, Dhaka
Expected Completion Date April 2027
Status Updated March, 2026
Back to all projects
Birchwood

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Foundation work Pile completed, Pile cap 100% completed
02 Super Structure work 100%
03 Block Work Common Area 70 %
04 Electrical conducting work N/A
05 Door frame fitting work N/A
06 Sanitary & plumbing line work N/A
07 In side Plastering work N/A
08 Electrical cable wiring work N/A
09 Wall tiles work N/A
10 Common sanitary & Plumbing line work N/A
11 Outside plastering work N/A
12 Floor tiles/Marble work N/A
13 L.C.C work N/A
14 Grill & Railing work N/A
15 Inside paint & Polishing work N/A
16 Switch -Socket fitting work N/A
17 Outside paint work N/A
18 Door shutter work N/A
19 Aluminum work N/A
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work N/A
24 Roof top finishing work

 

N/A
25 Roof top Gardening work G.F Garden work N/A

 