Bliss

Block D, Bashundhara R/A

Expected Completion Date

July 2028

Status Updated

January, 2026

SL. No Name of the work Location Progress details Remarks
01 Pile Work Pile 100% complete.  
02 Foundation work Foundation 100% Complete  
03 Super Structure work 1st floor

 

Roof slab Complete

 

 
04 Electrical conduiting work      
05 Door frame fitting work      
06 Sanitary & plumbing line work      
07 In side Plastering work Gr. Floor Ceiling

 

60%  Complete

 

 
08 Electrical cable wiring work      
09 Wall tiles work      
10 Common sanitary & Plumbing line work      
11 Outside plastering work      
12 Floor tiles/Marble work      
13 L.C.C work    

 

 
14 Grill & Railing work      
15 Inside paint & Polishing work      
16 Switch -Socket fitting work      
17 Outside paint work      
18 Door shutter work      
19 Aluminum work      
20 Tiles Pointing work & Marble finishing work      
21 Commode – Basin fitting work and C.P fittings work      
22 Lift/Generator /Substation /Solar work      
23 Boundary wall /Ground floor development work      
24 Roof top finishing work      
25 Roof top Gardening work G.F Garden work      

 

16604