bti Celebration Point

Plot: 3 & 5, Road: 113/A, Gulshan-2, Dhaka-1212

Bliss

Bashundhara R/A, Dhaka
Expected Completion Date July 2028
Status Updated March, 2026
Back to all projects
Bliss

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Location Progress details Remarks
01 Pile Work Pile 100% completed.  
02 Foundation work Foundation 100% Complete  
03 Super Structure work 4th floor Roof Slab casting Complete  
04 Electrical conduiting work      
05 Door frame fitting work      
06 Sanitary & plumbing line work      
07 In side Plastering work of ceiling GF

1st floor

100%  Complete

100% Complete

 
08 Electrical cable wiring work      
09 Wall tiles work      
10 Common sanitary & Plumbing line work      
11 Outside plastering work      
12 Floor tiles/Marble work      
13 L.C.C work    

 

 
14 Grill & Railing work      
15 Inside paint & Polishing work      
16 Switch -Socket fitting work      
17 Outside paint work      
18 Door shutter work      
19 Aluminum work      
20 Tiles Pointing work & Marble finishing work      
21 Commode – Basin fitting work and C.P fittings work      
22 Lift/Generator /Substation /Solar work      
23 Boundary wall /Ground floor development work G/F 70% Complete  
24 Roof top finishing work      
25 Roof top Gardening work G.F Garden work      