Expected Completion Date
June 2026
Status Updated
January, 2026
| SL. No | Name of the work | Location | Progress details
|
Remarks |
| 01 | Foundation work | 100% completed. | ||
| 02 | Super Structure work | 99.7% Completed | ||
| 03 | Block Work | Apartment =A2
Apartment =B2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Apartment =C10 Apartment =D10 Apartment =E10 Apartment =C11 Apartment =D11 Apartment =E11 Apartment =C12 Apartment =D12 Apartment =E12 Apartment =C13 Apartment =D13 Apartment =E13 Roof top
|
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 99.9 % Complete |
|
| 04 | Electrical conduiting work | Apartment =A2
Apartment =B2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Apartment =C10 Apartment =D10 Apartment =E10 Apartment =C11 Apartment =D11 Apartment =E11 Apartment =C12 Apartment =D12 Apartment =E12 Apartment =C13 Apartment =D13 Apartment =E13 |
99% Complete
99% Complete 99% Complete 99% Complete 99%. Complete 99% Complete 99% Complete 99% Complete 99% Complete 99% Complete 99% Complete 99% Complete 99% Complete 99% Complete 99% Complete 99% Complete 99% Complete 99% Complete 99% Complete 99% Complete 99% Complete 99% Complete 99% Complete 99% Complete 99% Complete 99% Complete 99% Complete 99% Complete |
|
| 05 | Door frame fitting work | Apartment =A2
Apartment =B2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Apartment =C10 Apartment =D10 Apartment =E10 Apartment =C11 Apartment =D11 Apartment =E11 Apartment =C12 Apartment =D12 Apartment =E12 Apartment =C13 Apartment =D13 Apartment =E13 |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete |
|
| 06 | Sanitary and plumbing work | Apartment =A2
Apartment =B2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Apartment =C10 Apartment =D10 Apartment =E10 Apartment =C11 Apartment =D11 Apartment =E11 Apartment =C12 Apartment =D12 Apartment =E12 Apartment =C13 Apartment =D13 Apartment =E13 |
90% Complete
90% Complete 90% Complete 90% Complete 90% Complete 90% Complete 90% Complete 90% Complete 96% Complete 96% Complete 96% Complete 96% Complete 96% Complete 96% Complete 96% Complete 96% Complete 96% Complete 96% Complete 96% complete 95% Complete 95% Complete 95% Complete 98% Complete 98% Complete 98% Complete 98% Complete 98% Complete 98% Complete
|
|
| 07 | In side Plastering work | Apartment =A2
Apartment =B2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Apartment =C10 Apartment =D10 Apartment =E10 Apartment =C11 Apartment =D11 Apartment =E11 Apartment =C12 Apartment =D12 Apartment =E12 Apartment =C13 Apartment =D13 Apartment =E13 |
90% Complete
90% Complete 90% Complete 90% Complete 90% Complete 90% Complete 90% Complete 93% Complete 93% Complete 93% Complete 93% Complete 90% Complete 90% Complete 93% Complete 95% Complete 95% Complete 98% Complete 98% Complete 98% Complete 98% Complete 98% Complete 98% Complete 98% Complete 98% Complete 98% Complete 98% Complete 9% Complete 98% Complete |
|
| 08 | Electrical cable wiring work | 88 % complete | ||
| 09 | Wall tiles work | 85% complete | ||
| 10 | Common sanitary & Plumbing line work |
60 % complete |
||
| 11 | Outside plastering work | 99 % complete | ||
| 12 | Floor tiles/Marble work | 85 % complete | ||
| 13 | L.C.C work | 100 % Complete
|
||
| 14 | Grill & Railing work | 87 % complete | ||
| 15 | Inside paint & Polishing work | 25 % complete | ||
| 16 | Switch -Socket fitting work | |||
| 17 | Outside paint work | 4 % complete | ||
| 18 | Door shutter work | Main door shutter only received | ||
| 19 | Aluminum work | 2 % complete
|
||
| 20 | Tiles Pointing work & Marble finishing work | |||
| 21 | Commode – Basin fitting work and C.P fittings work |
|
||
| 22 | Lift/Generator /Substation /Solar work | Generator only received | ||
| 23 | Boundary wall /Ground floor development work | 20 % complete | ||
| 24 | Roof top finishing work | 65% complete | ||
| 25 | Roof top Gardening work G.F Garden work | 48% complete |