Blue Ribbon Homes

Bashundhara R/A, Dhaka

Expected Completion Date

January 2026

Status Updated

November, 2024

SL. No Name of the work Progress details Remarks
01 Foundation work 100% completed  
02 Super Structure work 12th floor roof slab shuttering work is in process  
03 Block Work 47 % complete  
04 Electrical conduiting work 40 % complete  
05 Door frame fitting work    
06 Sanitary & plumbing line work    
07 In side Plastering work 30 % complete  
08 Electrical cable wiring work    
09 Wall tiles  work    
10 Common sanitary & Plumbing line work    
11 Outside plastering work    
12 Floor tiles/Marble work    
13 L.C.C work    
14 Grill & Railing work    
15 Inside paint & Polishing work    
16 Switch -Socket fitting work    
17 Outside paint work    
18 Door shutter work    
19 Aluminum work    
20 Tiles Pointing work & Marble finishing work    
21 Commode – Basin fitting work and C.P fittings work    
22 Lift/Generator /Substation /Solar work    
23 Boundary wall /Ground floor development work    
24 Roof top finishing work    
25 Roof top Gardening work G.F Garden work    