Blue Ribbon Homes

Bashundhara R/A, Dhaka

Expected Completion Date

June 2026

Status Updated

January, 2026

SL. No Name of the work Location Progress details

 

Remarks
01 Foundation work   100% completed.  
02 Super Structure work   99.7% Completed  
03 Block Work Apartment =A2

Apartment =B2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment =A8

Apartment =B8

Apartment =A9

Apartment =B9

Apartment =C10

Apartment =D10

Apartment =E10

Apartment =C11

Apartment =D11

Apartment =E11

Apartment =C12

Apartment =D12

Apartment =E12

Apartment =C13

Apartment =D13

Apartment =E13

Roof top

 

 

 100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

99.9 % Complete

 
04 Electrical conduiting work Apartment =A2

Apartment =B2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment =A8

Apartment =B8

Apartment =A9

Apartment =B9

Apartment =C10

Apartment =D10

Apartment =E10

Apartment =C11

Apartment =D11

Apartment =E11

Apartment =C12

Apartment =D12

Apartment =E12

Apartment =C13

Apartment =D13

Apartment =E13

99% Complete

99% Complete

99% Complete

99% Complete

99%. Complete

99% Complete

99% Complete

99% Complete

99% Complete

99% Complete

99% Complete

99% Complete

99% Complete

99% Complete

99% Complete

99% Complete

99% Complete

99% Complete

99% Complete

99% Complete

99% Complete

99% Complete

99% Complete

99% Complete

99% Complete

99% Complete

99% Complete

99% Complete

 
05 Door frame fitting work Apartment =A2

Apartment =B2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment =A8

Apartment =B8

Apartment =A9

Apartment =B9

Apartment =C10

Apartment =D10

Apartment =E10

Apartment =C11

Apartment =D11

Apartment =E11

Apartment =C12

Apartment =D12

Apartment =E12

Apartment =C13

Apartment =D13

Apartment =E13

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 
06 Sanitary and plumbing work Apartment =A2

Apartment =B2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment =A8

Apartment =B8

Apartment =A9

Apartment =B9

Apartment =C10

Apartment =D10

Apartment =E10

Apartment =C11

Apartment =D11

Apartment =E11

Apartment =C12

Apartment =D12

Apartment =E12

Apartment =C13

Apartment =D13

Apartment =E13

90% Complete

90% Complete

90% Complete

90% Complete

90% Complete

90% Complete

90% Complete

90% Complete

96% Complete

96% Complete

96% Complete

96% Complete

96% Complete

96% Complete

96% Complete

96% Complete

96% Complete

96% Complete

96% complete

95% Complete

95% Complete

95% Complete

98% Complete

98% Complete

98% Complete

98% Complete

98% Complete

98% Complete

 

 
07 In side Plastering work Apartment =A2

Apartment =B2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment =A8

Apartment =B8

Apartment =A9

Apartment =B9

Apartment =C10

Apartment =D10

Apartment =E10

Apartment =C11

Apartment =D11

Apartment =E11

Apartment =C12

Apartment =D12

Apartment =E12

Apartment =C13

Apartment =D13

Apartment =E13

90% Complete

90% Complete

90% Complete

90% Complete

90% Complete

90% Complete

90% Complete

93% Complete

93% Complete

93% Complete

93% Complete

90% Complete

90% Complete

93% Complete

95% Complete

95% Complete

98% Complete

98% Complete

98% Complete

98% Complete

98% Complete

98% Complete

98% Complete

98% Complete

98% Complete

98% Complete

9% Complete

98% Complete

 
08 Electrical cable wiring work   88 %  complete  
09 Wall tiles work   85% complete  
10 Common sanitary & Plumbing line work    

60 % complete

 
11 Outside plastering work   99 % complete  
12 Floor tiles/Marble work   85 % complete  
13 L.C.C work   100 % Complete

 

 

 
14 Grill & Railing work   87 % complete  
15 Inside paint & Polishing work   25 % complete  
16 Switch -Socket fitting work      
17 Outside paint work   4 % complete  
18 Door shutter work     Main door shutter only received
19 Aluminum work   2 % complete

 

 
20 Tiles Pointing work & Marble finishing work      
21 Commode – Basin fitting work and C.P fittings work    

 

 
22 Lift/Generator /Substation /Solar work     Generator only received
23 Boundary wall /Ground floor development work   20 % complete  
24 Roof top finishing work   65% complete  
25 Roof top Gardening work G.F Garden work   48% complete  