Expected Completion Date
January 2026
Status Updated
November, 2024
SL. No | Name of the work | Location | Progress details | Remarks |
01 | Foundation work | 100% completed. | ||
02 | Super Structure work | 88 % Completed | ||
03 | Block Work | Apartment =A2
Apartment =B2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Apartment =C10 Apartment =D10 Apartment =E10 Apartment =C11 Apartment =D11 Apartment =E11 Apartment =C12 Apartment =D12 Apartment =E12 Apartment =C13 Apartment =D13 Apartment =E13 |
75% Complete
75% Complete 90% Complete 95% Complete 95% Complete 95% Complete 90% Complete 90% Complete 70% Complete 85% Complete 60% Complete 60% Complete 60% Complete 60% Complete 20% Complete 15% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete |
|
04 | Electrical conduiting work | Apartment =A2
Apartment =B2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Apartment =C10 Apartment =D10 Apartment =E10 Apartment =C11 Apartment =D11 Apartment =E11 Apartment =C12 Apartment =D12 Apartment =E12 Apartment =C13 Apartment =D13 Apartment =E13 |
50% Complete
50% Complete 60% Complete 95% Complete 90% Complete 95% Complete 70% Complete 70% Complete 70% Complete 80% Complete 45% Complete 45% Complete 45% Complete 45% Complete 30% Complete 30% Complete 30% Complete 30% Complete 30% Complete 30% Complete 30% Complete 30% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete |
|
05 | Door frame fitting work | Apartment =A2
Apartment =B2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Apartment =C10 Apartment =D10 Apartment =E10 Apartment =C11 Apartment =D11 Apartment =E11 Apartment =C12 Apartment =D12 Apartment =E12 Apartment =C13 Apartment =D13 Apartment =E13 |
00% Complete
00% Complete 00% Complete 90% Complete 90% Complete 90% Complete 80% Complete 85% Complete 00% Complete 70% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete |
|
06 | Sanitary and plumbing work | Apartment =A2
Apartment =B2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Apartment =C10 Apartment =D10 Apartment =E10 Apartment =C11 Apartment =D11 Apartment =E11 Apartment =C12 Apartment =D12 Apartment =E12 Apartment =C13 Apartment =D13 Apartment =E13 |
08% Complete
08% Complete 08% Complete 08% Complete 08% Complete 08% Complete 08% Complete 08% Complete 08% Complete 08% Complete 05% Complete 05% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete |
|
07 | In side Plastering work | Apartment =A2
Apartment =B2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Apartment =C10 Apartment =D10 Apartment =E10 Apartment =C11 Apartment =D11 Apartment =E11 Apartment =C12 Apartment =D12 Apartment =E12 Apartment =C13 Apartment =D13 Apartment =E13 |
30% Complete
30% Complete 30% Complete 90% Complete 80% Complete 80% Complete 30% Complete 80% Complete 30% Complete 30% Complete 30% Complete 30% Complete 30% Complete 30% Complete 30% Complete 30% Complete 25% Complete 25% Complete 25% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete |
|
08 | Electrical cable wiring work | |||
09 | Wall tiles work | |||
10 | Common sanitary & Plumbing line work |
|
||
11 | Outside plastering work | |||
12 | Floor tiles/Marble work | |||
13 | L.C.C work |
|
||
14 | Grill & Railing work | |||
15 | Inside paint & Polishing work | |||
16 | Switch -Socket fitting work | |||
17 | Outside paint work | |||
18 | Door shutter work | |||
19 | Aluminum work | |||
20 | Tiles Pointing work & Marble finishing work | |||
21 | Commode – Basin fitting work and C.P fittings work |
|
||
22 | Lift/Generator /Substation /Solar work | |||
23 | Boundary wall /Ground floor development work | |||
24 | Roof top finishing work | |||
25 | Roof top Gardening work G.F Garden work |
16604