Expected Completion Date
January 2025
Status Updated
November, 2024
SL. No | Name of the work | Progress details |
Foundation work | 100% Completed | |
Super Structure work | 100% completed | |
Block work | A-1=100%, A-2=100%, A-3= 100%, A-4=100%, A-5=100%, A-6=100%. | |
Electrical conduit work | A-1=100%, A-2=100%, A-3= 100%, A-4=100%, A-5=100%, A-6=100%. | |
Door frame fitting work | A-1=100%, A-2=100%, A-3=100%, A-4=100%, A-5=100%, A-6=100%. | |
Sanitary & plumbing line work | A-1=98%, A-2=98%, A-3= 98%, A-4=95%, A-5=95%, A-6=95%. | |
In side Plastering work | A-1=100%, A-2=100%, A-3= 100%, A-4=100%, A-5=100%, A-6=100%. | |
Electrical cable wiring work | A-1=90%, A-2=95%, A-3= 95%, A-4=94%, A-5=95%, A-6=93%. | |
Wall tiles work | A-1=100%, A-2=100%, A-3= 100%, A-4=100%, A-5=100%, A-6=100%. | |
Common sanitary & Plumbing line work | 60% | |
Outside plastering work | 95% | |
Marble work | 100% | |
General floor Tiles | 98% | |
L.C.C work | 10% | |
Grill & Railing work | 95% | |
Inside paint & Polishing work | 70% | |
Switch -Socket fitting work | 40% | |
Aluminum/Glazing work | 70% | |
Outside paint work | 60% | |
Door shutter work | 75% | |
Tiles Pointing work & Marble finishing work | 80% | |
Commode – Basin fitting work and C.P fittings work | 60% | |
Lift/Generator /Substation /Solar work | 75% | |
Boundary wall /Ground floor development work | 80% | |
Roof top finishing work | 80% | |
Roof top Gardening work | 55% |