Expected Completion Date
January 2025
Status Updated
February, 2025
| SL. No | Name of the work | Progress details |
| Foundation work | 100% Completed | |
| Super Structure work | 100% completed | |
| Block work | A-1=100%, A-2=100%, A-3= 100%, A-4=100%, A-5=100%, A-6=100%. | |
| Electrical conduit work | A-1=100%, A-2=100%, A-3= 100%, A-4=100%, A-5=100%, A-6=100%. | |
| Door frame fitting work | A-1=100%, A-2=100%, A-3=100%, A-4=100%, A-5=100%, A-6=100%. | |
| Sanitary & plumbing line work | A-1=100%, A-2=100%, A-3=100%, A-4=100%, A-5=100%, A-6=100%. | |
| In side Plastering work | A-1=100%, A-2=100%, A-3= 100%, A-4=100%, A-5=100%, A-6=100%. | |
| Electrical cable wiring work | A-1=100%, A-2=100%, A-3= 100%, A-4=100%, A-5=100%, A-6=100%. | |
| Wall tiles work | A-1=100%, A-2=100%, A-3= 100%, A-4=100%, A-5=100%, A-6=100%. | |
| Common sanitary & Plumbing line work | 100% | |
| Outside plastering work | 100% | |
| Marble work | 100% | |
| General floor Tiles | 100% | |
| L.C.C work | 100% | |
| Grill & Railing work | 100% | |
| Inside paint & Polishing work | 100% | |
| Switch -Socket fitting work | 100% | |
| Aluminum/Glazing work | 100% | |
| Outside paint work | 100% | |
| Door shutter work | 100% | |
| Tiles Pointing work & Marble finishing work | 100% | |
| Commode – Basin fitting work and C.P fittings work | 100% | |
| Lift/Generator /Substation /Solar work | 100% | |
| Boundary wall /Ground floor development work | 100% | |
| Roof top finishing work | 100% | |
| Roof top Gardening work | 90% |