Breezy Homes

Bashundhara R/A, Dhaka

Expected Completion Date

January 2025

Status Updated

November, 2024

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 100% completed
  Block work A-1=100%, A-2=100%, A-3= 100%, A-4=100%, A-5=100%, A-6=100%.
  Electrical  conduit work A-1=100%, A-2=100%, A-3= 100%, A-4=100%, A-5=100%, A-6=100%.
  Door frame fitting work A-1=100%, A-2=100%, A-3=100%,         A-4=100%, A-5=100%, A-6=100%.
  Sanitary & plumbing line  work A-1=98%, A-2=98%, A-3= 98%, A-4=95%, A-5=95%, A-6=95%.
  In side Plastering work A-1=100%, A-2=100%, A-3= 100%, A-4=100%, A-5=100%, A-6=100%.
  Electrical cable wiring work A-1=90%, A-2=95%, A-3= 95%, A-4=94%, A-5=95%, A-6=93%.
  Wall tiles  work A-1=100%, A-2=100%, A-3= 100%, A-4=100%, A-5=100%, A-6=100%.
  Common sanitary & Plumbing line work 60%
  Outside plastering work 95%
  Marble work 100%
  General floor Tiles 98%
  L.C.C work 10%
  Grill & Railing work 95%
  Inside paint & Polishing work 70%
  Switch -Socket fitting work 40%
  Aluminum/Glazing work 70%
  Outside paint work 60%
  Door shutter work 75%
  Tiles Pointing work & Marble finishing work 80%
  Commode – Basin fitting work and C.P fittings work 60%
  Lift/Generator /Substation /Solar work 75%
  Boundary wall /Ground floor development work 80%
  Roof top finishing work 80%
  Roof top Gardening work 55%

 