Breezy Homes

Bashundhara R/A, Dhaka

Completion Date

September 2024

Status Updated

March, 2024

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 100% completed
  Block work A-1=95%, A-2=95%, A-3= 95%, A-4=95%, A-5=95%, A-6=95%.
  Electrical  conduit work A-1=90%, A-2=90%, A-3= 90%, A-4=90%, A-5=90%, A-6=90%.
  Door frame fitting work A-1=100%, A-2=100%, A-3=100%,         A-4=100%, A-5=100%, A-6=100%.
  Sanitary & plumbing line  work A-1=90%, A-2=90%, A-3= 90%, A-4=90%, A-5=90%, A-6=90%.
  In side Plastering work A-1=90%, A-2=90%, A-3= 70%, A-4=90%, A-5=90%, A-6=50%.
  Electrical cable wiring work A-1=30%, A-2=30%, A-3= 30%, A-4=30%, A-5=30%, A-6=30%.
  Wall tiles  work A-1=70%, A-2=70%, A-3= 70%, A-4=70%, A-5=70%, A-6=70%.
  Common sanitary & Plumbing line work N/A
  Outside plastering work 50%
  Floor tiles/Marble work N/A
  L.C.C work N/A
  Grill & Railing work N/A
  Inside paint & Polishing work N/A
  Switch -Socket fitting work N/A
  Aluminum/Glazing work N/A
  Outside paint work N/A
  Door shutter work N/A
  Tiles Pointing work & Marble finishing work N/A
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work N/A
  Boundary wall /Ground floor development work N/A
  Roof top finishing work N/A
  Roof top Gardening work N/A